QCI-NABET accreditation of EIA consultant organisations (EIA Coordinator and Functional Area Expert approval)

India · National Accreditation Board for Education and Training, Quality Council of India · unverified source

39practice questions written to this syllabus
1subjects

What QCI-NABET accreditation of EIA consultant organisations is

QCI-NABET accreditation of EIA consultant organisations (EIA Coordinator and Functional Area Expert approval) is a professional certification run by National Accreditation Board for Education and Training, Quality Council of India, for candidates in India.

Format

Not a public written exam: organisations are accredited after document review and assessment, and individual EIA coordinators and functional area experts are approved through assessment interviews against sector-specific competence criteria.

Sections

We have not been able to confirm these details against the exam body's own specification, so fees, dates and pass marks are left out on purpose.

Check the current format, eligibility, fees and dates on the official site: nabet.qci.org.in.

How it has changed

In India an EIA report for environmental clearance must be prepared by an accredited consultant, so this is the working credential of an EIA practitioner.

Official source: nabet.qci.org.in

8 practice questions, worked

Original questions written to this exam's published syllabus and pattern. Not past papers.

1. For comparing alternative routes of a pipeline through sensitive landscapes, which method is most suitable?

  1. Weighted GIS overlay analysis
  2. A simple checklist of impact types
  3. A questionnaire checklist sent to the proponent
  4. An ad hoc expert panel without maps
Answer and working

A. Weighted GIS overlay analysis

Overlay analysis in GIS maps habitats, slopes, settlements and heritage along each corridor and scores suitability, which suits spatial comparison of routes. Checklists and ad hoc panels lack spatial analysis.

Environmental Impact Assessment & Strategic Environmental Assessment · Impact identification: checklists, matrices, networks, overlays

2. Settlement and roadside businesses springing up along a new rural road are an example of what kind of impact?

  1. Direct impact
  2. Residual impact
  3. Induced impact
  4. Transboundary impact
Answer and working

C. Induced impact

Induced impacts arise from activities the project stimulates. Direct impacts are caused by the project itself (land take for the road); residual impacts remain after mitigation; transboundary impacts cross borders.

Environmental Impact Assessment & Strategic Environmental Assessment · Impact prediction and evaluation of significance

3. For a large canal irrigation project, which issue would scoping most clearly identify as key?

  1. Electromagnetic radiation from mobile phone towers in nearby towns
  2. Waterlogging and salinity in the command area and reduced flows downstream
  3. Radioactive waste storage at the project headworks
  4. Light pollution affecting astronomical observatories
Answer and working

B. Waterlogging and salinity in the command area and reduced flows downstream

Irrigation schemes typically raise water tables and salinity without drainage, and diversions reduce downstream flows for ecosystems and users; resettlement and vector-borne disease are other common issues. The other options are not typical of irrigation.

Environmental Impact Assessment & Strategic Environmental Assessment · Scoping and terms of reference

4. Which four stages make up the environmental clearance process under India's EIA Notification 2006?

  1. Planning, design, construction and commissioning of the project
  2. Screening, scoping, public consultation and appraisal
  3. Inspection, sampling, prosecution and closure of the industry
  4. Application, payment, inspection and automatic approval after 30 days
Answer and working

B. Screening, scoping, public consultation and appraisal

The Notification sets screening (Category B only), scoping (ToR), public consultation and appraisal. The other sequences describe project phases, enforcement or an invented deemed-approval process.

Environmental Impact Assessment & Strategic Environmental Assessment · Legal frameworks: NEPA, EU EIA Directive, India EIA Notification and others

5. Under India's EIA Notification 2006, which body appraises Category A projects?

  1. The Expert Appraisal Committee for the central environment ministry
  2. The State Expert Appraisal Committee
  3. The district collector's office
  4. The State Pollution Control Board alone
Answer and working

A. The Expert Appraisal Committee for the central environment ministry

Category A projects are appraised at central level by Expert Appraisal Committees advising the MoEFCC; Category B projects go to SEIAA advised by SEAC. The SPCB conducts public hearings but does not appraise.

Environmental Impact Assessment & Strategic Environmental Assessment · Legal frameworks: NEPA, EU EIA Directive, India EIA Notification and others

6. Which item belongs in an EIA's terms of reference?

  1. The amount of compensation each villager will finally receive after construction is complete
  2. The proponent's annual profit forecast and expected dividend to shareholders
  3. Baseline parameters, sampling seasons and frequency, and prediction methods to be used
  4. The name of the judge who will hear any appeal against the clearance
Answer and working

C. Baseline parameters, sampling seasons and frequency, and prediction methods to be used

ToR specify the project description, study area, baseline parameters and seasons, prediction methods, significance criteria, mitigation, EMP, consultation and report contents. Final compensation, profits and judges are not ToR items.

Environmental Impact Assessment & Strategic Environmental Assessment · Scoping and terms of reference

7. An effluent limit is 30 mg/L BOD and the EMP sets an action threshold at 80 % of the limit. Above what value must managers investigate?

  1. 30 mg/L
  2. 24 mg/L
  3. 37.5 mg/L
  4. 6 mg/L
Answer and working

B. 24 mg/L

Action threshold = 0.80 × 30 = 24 mg/L. 30 is the legal limit itself; 37.5 divides by 0.8; 6 is the difference between limit and threshold.

Environmental Impact Assessment & Strategic Environmental Assessment · Environmental management plans and monitoring

8. Two identical machines each produce 70 dB at a receptor. What is the combined level?

  1. 140 dB
  2. 70 dB
  3. 73 dB
  4. 35 dB
Answer and working

C. 73 dB

L = 10 log10(10^7 + 10^7) = 70 + 10 log10 2 = 73 dB. Decibels add logarithmically, so 140 is wrong; 70 ignores the second source; 35 halves the level.

Environmental Impact Assessment & Strategic Environmental Assessment · Impact prediction and evaluation of significance

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock all 39 questions — QCI-NABET accreditation of EIA consultant organisations (EIA Coordinator and Functional Ar

US$10 a month · one price worldwide · cancel any time

  • Every practice question for this course, with explanations
  • Timed papers for the exams this course leads to
  • Ask Laisha to explain any topic — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.