ICAR AICE-JRF/SRF (PhD admission and fellowship) · India · National Testing Agency for ICAR
Original practice questions written to the published syllabus · not past papersICAR AICE-JRF/SRF (PhD admission and fellowship) is a PhD, fellowship and lectureship exam run by National Testing Agency for ICAR, for candidates in India. LAN-based CBT, 2 hours, 120 MCQs, 480 marks, +4 / -1. 2026 exam on 4 July 2026. 72 subjects at 122 cities.
Source: cdnbbsr.s3waas.gov.in.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
The heaviest source of questions. Expect definitions and attributions (Skinner, Hayes and Wheelwright, Taylor, Gilbreths, Shewhart, Deming, Juran, Crosby, Ishikawa, Taguchi, Ohno, Shingo, Orlicky, Hammer and Champy, Miles, Nakajima); layout types and line balancing (cycle time, minimum stations, efficiency, balance delay); location methods (factor rating, centre of gravity, locational break-even, Weber's material index); level, chase and mixed aggregate plans; MPS, time fences and ATP; SPT, EDD, critical ratio and Johnson's rule; method study symbols and steps, normal and standard time; ABC, VED and FSN; MRP netting, MRP II and ERP; JIT, kanban number, seven wastes, 5S, SMED; cost of quality, control-chart limits, Cp and Cpk, OC curves, AQL and LTPD; HACCP principles, ISO 9001 and 22000, BIS and AGMARK; maintenance types, availability, OEE and TPM.
Designing and running production: location, layout, planning, inventory, quality and productivity, applied to processing plants and agribusiness operations.
Our 130 ICAR AICE-JRF/SRF questions in this subject: 33 easy, 72 medium, 25 hard, across 16 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to ICAR AICE-JRF/SRF and are not shown on any other exam's page.
A juice bottling plant must fill 60,000 bottles a day. Each filling machine is rated at 1,500 bottles per hour, the plant runs 16 hours a day, and machines achieve 80% of rated output on average. How many machines are needed?
B. 4 machines
Output per machine per day = 1,500 x 16 x 0.8 = 19,200. Machines = 60,000/19,200 = 3.125, rounded up to 4; rounding down to 3 leaves demand unmet. Ignoring the 80% factor gives 2.5, which also tempts students to answer 3; using 24 hours instead of 16 gives 2.08, wrongly rounded to 2. 5 over-provides.
A sugar mill's crushing line has four sequential stages with hourly capacities of 120 t (cane preparation), 100 t (milling), 90 t (clarification) and 110 t (evaporation). What is the line's capacity, and where should the next investment go?
C. 90 t per hour; expand clarification, the bottleneck
In a sequential process the system capacity equals the slowest stage, here clarification at 90 t/h. Averaging stages (105) or taking the first stage (120) overstates capacity; adding capacity elsewhere adds nothing until the bottleneck is relieved, after which milling at 100 t/h becomes the new bottleneck.
As a processing operation moves from job-shop towards continuous-flow production, which change is expected?
B. Unit variable cost falls while fixed cost and capital intensity rise
Continuous processes spread high fixed cost over large volumes, so unit variable cost falls, but flexibility falls and work-in-process is lower. Craft skills matter most in job shops; continuous plants need monitoring skills.
A dal mill compares two sites. Site A: fixed cost 3,000,000 currency units a year, variable cost 400 per tonne. Site B: fixed cost 5,000,000 currency units a year, variable cost 300 per tonne. At what annual volume do the two sites cost the same?
A. 20,000 tonnes
Set 3,000,000 + 400V = 5,000,000 + 300V, so V = (difference in fixed cost)/(difference in variable cost) = 2,000,000/100 = 20,000 tonnes. Adding the fixed costs (80,000) or the variable costs (2,857) instead of subtracting them gives the wrong crossover; 5,000 divides the fixed-cost gap by Site A's full variable cost of 400 instead of the 100 gap.
A custom flour mill has five orders on one machine, with processing time and due date in days: P 6 and 10, Q 2 and 6, R 8 and 18, S 3 and 15, T 9 and 23. Using the shortest-processing-time rule, what is the mean flow time?
C. 13.0 days
SPT order Q, S, P, R, T gives completion times 2, 5, 11, 19, 28; mean = 65/5 = 13.0. 15.4 is FCFS and 13.6 is EDD; 28/5 = 5.6 is mean processing time, not flow time.
A dairy cooperative is choosing an ERP system. Which feature is most specific to its needs rather than to general manufacturing?
D. Procurement from many farmers with quality-based payment and lot traceability
General ERP covers accounts, payroll and sales. Agribusinesses also need grower accounts with payment on fat and SNF or sugar content, batch traceability and shelf-life control, which standard packages may lack without adaptation.
Heijunka in the Toyota Production System refers to:
C. Levelling production volume and mix over time
Heijunka is level, mixed-model scheduling. Stopping the line is jidoka; mistake-proofing is poka-yoke; card signals are kanban.
Which list gives Womack and Jones's five lean principles in order?
D. Specify value, identify the value stream, flow, pull, perfection
Lean Thinking (1996) set out value, value stream, flow, pull and perfection. PDCA is the Shewhart-Deming cycle, DMAIC is Six Sigma, and 5S is workplace organisation.
In a flour mill, lorries queue for two hours at the weighbridge before unloading. In lean terms this is primarily:
D. Waiting waste
Idle time of people, vehicles or material is waiting waste. Over-processing adds work the customer does not value; defects are rework or scrap.
For the same filler (subgroups of 5, average range 8 g, D3 = 0, D4 = 2.114), what are the R chart limits?
D. UCL 16.912 g, LCL 0
R chart: UCL = D4 x R-bar = 2.114 x 8 = 16.912; LCL = D3 x R-bar = 0. The A2 factor belongs to the X-bar chart (8 +/- 4.616 gives 12.616 and 3.384); a symmetric lower limit (8 - 8.912 = -0.912) is wrong because D3 = 0 for n = 5; 24 uses 3 x R-bar.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Do these early in revision so they are fast on the day.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.