UGC-NET (June 2025) · India · National Testing Agency
Original practice questions written to the published syllabus · not past papersUGC-NET (June 2025) is a PhD, fellowship and lectureship exam run by National Testing Agency, for candidates in India. CBT (since Dec 2018). Paper I 50 questions / 100 marks; Paper II 100 questions / 200 marks; 180 minutes total; +2, no negative marking.
Source: ugcnet.nta.ac.in.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
Production and operations management at MBA level: process-product matrix, capacity measures, layout, aggregate planning, scheduling rules, work study, inventory classification, MRP and ERP, JIT and lean, TQM thinkers, SPC and acceptance sampling, ISO standards, BPR, value engineering and maintenance. Mostly one-step conceptual and matching questions with occasional short numericals.
Designing and running production: location, layout, planning, inventory, quality and productivity, applied to processing plants and agribusiness operations.
Our 124 UGC-NET questions in this subject: 33 easy, 68 medium, 23 hard, across 16 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to UGC-NET and are not shown on any other exam's page.
A cooperative dairy replaces manual pouch filling with automatic fillers. Litres per labour-hour rise 40% but capital charges rise sharply. Which statement is correct?
C. Labour productivity rose, but only a multifactor measure shows whether overall productivity rose
A partial measure (labour productivity) ignores the extra capital used. Multifactor or total productivity, with all inputs in money terms, shows whether the trade of labour for capital raised efficiency overall. Capital productivity may well fall.
Which forecasting method gathers anonymous opinions from a panel of experts in several rounds, with feedback, until views converge?
A. Delphi method
The Delphi method uses anonymity and iterated feedback to avoid dominance by strong personalities. Jury of executive opinion meets face to face; sales-force composite adds up salespeople's estimates; exponential smoothing is a time-series method.
A pilot work-sampling study finds a forklift idle about 25% of the time. How many random observations are needed to estimate idle time within plus or minus 5 percentage points at 95% confidence (z = 1.96)?
B. 289
n = z^2 p(1-p)/e^2 = 1.96^2 x 0.25 x 0.75/0.05^2 = 288.1, rounded up to 289. Reading 5% as relative to p (e = 0.0125) gives about 4,610; forgetting to square z gives 147. 385 uses the conservative p = 0.5 instead of the pilot estimate of 0.25.
On a flow process chart using ASME symbols, what does a large arrow represent?
A. Transport
ASME symbols: operation is a circle, inspection a square, transport an arrow, delay a D shape, storage a triangle.
What is the correct order of the basic steps of method study?
B. Select, record, examine, develop, install, maintain
The ILO procedure is select the job, record the present method, examine it critically, develop a better method, install (after evaluating and defining it), and maintain it.
A juice carton contains 12 bottles, and each bottle takes one cap. The MPS calls for 200 cartons. There are 400 filled bottles and 300 caps on hand and no other stock. Using lot-for-lot, how many caps must be ordered?
A. 1,700
Gross bottles = 200 x 12 = 2,400; net bottles = 2,400 - 400 = 2,000. Caps are needed only for bottles to be made: gross caps 2,000, net caps 2,000 - 300 = 1,700. Exploding from gross bottles (2,100) skips netting at the bottle level, the classic MRP error.
A flour mill's cost of goods sold is 120,000,000 currency units a year and its average inventory is 30,000,000. What are inventory turnover and days of inventory (365-day year)?
A. 4 times; about 91 days
Turnover = COGS / average inventory = 12/3 = 4. Days of inventory = 365/4 = 91.25, about 91 days. Inverting the ratio or multiplying by 365 are the slips.
A rice mill buys most of its year's paddy in the three months after harvest. In terms of inventory function, this stock is mainly:
B. Anticipation stock
Anticipation stock is built ahead of need because supply or demand is seasonal. Cycle stock results from lot sizes; pipeline stock is in transit; decoupling stock separates stages.
The ISI mark on a product in India indicates certification by:
D. Bureau of Indian Standards
BIS runs product certification with the ISI mark (named after its predecessor, the Indian Standards Institution). AGMARK is from DMI; ISO does not certify products.
ISO 22000 is an international standard for:
A. Food safety management systems
ISO 22000 combines interactive communication, system management, prerequisite programmes and HACCP principles. ISO 9001 is QMS, ISO 14001 EMS, ISO 45001 OH&S.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Do these early in revision so they are fast on the day.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.