GATE — Environmental Science and Engineering (ES) · India · IITs and IISc on rotation (2027: IIT Madras)
Original practice questions written to the published syllabus · not past papersGATE — Environmental Science and Engineering (ES) is a postgraduate admission exam run by IITs and IISc on rotation (2027: IIT Madras), for candidates in India. Computer-based, 3 hours, 100 marks (15 General Aptitude + 85 subject). MCQ, MSQ and NAT question types with negative marking on MCQ only, as in all GATE papers.
Source: gate2026.iitg.ac.in.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
EIA process steps, screening and scoping, methods (checklists, Leopold matrix, networks, overlays, Battelle), impact prediction numericals (noise attenuation and decibel addition, mixing, dispersion), significance, EMP and Indian EIA Notification 2006 categories and stages.
The full EIA process as a practitioner runs it: screening, scoping, baseline studies, impact prediction, significance, mitigation hierarchy, environmental management plans, public consultation, review and follow-up, plus SEA and social impact assessment. The Agribusiness subject natural-resource-environmental-economics and the Agricultural Engineering waste subject each carry a one-unit introduction to EIA; this is the full subject.
Our 39 GATE ES questions in this subject: 16 easy, 18 medium, 5 hard, across 12 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to GATE ES and are not shown on any other exam's page.
Which three groups of criteria are used for case-by-case screening under Annex III of the EU EIA Directive?
A. Project characteristics, project location, and the type and characteristics of the impact
Annex III groups criteria into project characteristics (size, cumulation, resources, waste, risks), location (sensitivity, protected areas) and impact characteristics (magnitude, extent, probability, duration, reversibility, transboundary nature). The others are not screening criteria.
What role does the 'no-project' (no action) alternative play in EIA?
D. It describes the future without the project and serves as the reference for comparison
The no-action alternative is the baseline against which other alternatives' impacts are measured. It need not be chosen, it is expected in good practice and required under NEPA, and the mitigated project is a separate alternative.
For air quality baseline monitoring around a proposed industrial site, where should stations generally be located?
D. Upwind and downwind of the site, including at sensitive receptors such as villages
Stations upwind give background; downwind stations and receptor locations show where impacts will fall, informed by the wind rose. Monitoring only inside the site, only in a distant city or only upwind misses receptors.
In the Leopold matrix, what two values are entered in each relevant cell?
D. Magnitude and importance, each on a scale of 1 to 10
Leopold et al. (1971) asked for magnitude (extent or degree, a factual estimate) and importance (significance, a judgement), each scored 1–10. The matrix does not record costs, probabilities or area-duration pairs.
In the Battelle Environmental Evaluation System, how many parameter importance units (PIU) are distributed among the parameters?
A. 1000
Battelle distributes 1000 PIU among 78 parameters in four categories (ecology, environmental pollution, aesthetics, human interest). 100 is a scale, 78 is the number of parameters.
Overlay mapping as an EIA and planning method is most associated with whom?
B. Ian McHarg, Design with Nature (1969)
McHarg popularised overlaying maps of environmental factors to find suitable and sensitive areas. Leopold developed the matrix, Dee the Battelle system, and Arnstein the ladder of citizen participation.
A point source produces 85 dB at 10 m. Assuming free-field spreading (L2 = L1 − 20 log10(r2/r1)), what is the level at 80 m?
A. 66.9 dB
L = 85 − 20 log10(80/10) = 85 − 20 × 0.903 = 66.9 dB (about 6 dB per doubling, three doublings). 76.0 uses the line-source 10 log rule; 10.6 divides decibels by distance ratio; 37 subtracts 6 dB for each multiple of distance instead of each doubling.
What is an environmental management plan (EMP)?
A. An action plan setting out mitigation, responsibilities, timing, budget and monitoring
The EMP turns EIA commitments into an implementable plan with responsibilities, schedules, costs, indicators and reporting. Policies, maps and annual reports are different documents.
Baseline PM10 at a village is 72 µg/m³ against a standard of 100 µg/m³. Three proposed plants are each predicted to add 10 µg/m³ there. What is the cumulative concentration?
D. 102 µg/m³, which exceeds the standard
Cumulative = 72 + 3 × 10 = 102 µg/m³ > 100: each plant alone (82) appears acceptable but together they breach the standard. 30 ignores the baseline; 172 adds the standard.
Which EU directive requires SEA of certain plans and programmes?
A. Directive 2001/42/EC
The SEA Directive is 2001/42/EC. 2011/92/EU is the EIA Directive; 2000/60/EC the Water Framework Directive; 92/43/EEC the Habitats Directive.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Do these early in revision so they are fast on the day.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.