Original practice questions written to the published syllabus · not past papersGATE — Environmental Science and Engineering (ES) is a postgraduate admission exam run by IITs and IISc on rotation (2027: IIT Madras), for candidates in India. Computer-based, 3 hours, 100 marks (15 General Aptitude + 85 subject). MCQ, MSQ and NAT question types with negative marking on MCQ only, as in all GATE papers.
Source: gate2026.iitg.ac.in.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
The mathematics and statistics needed for every numerical question in this track: calculus and differential equations for growth and decay, probability and risk, regression and hypothesis tests, and sampling designs for field data. Experimental design and survey sampling in depth live in the Agricultural Statistics track; this subject covers the environmental applications.
Our 86 GATE ES questions in this subject: 20 easy, 41 medium, 25 hard, across 11 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to GATE ES and are not shown on any other exam's page.
A pollutant decays by dC/dt = −kC with k = 0.1 per day and C0 = 100 mg/L. What is C after 10 days?
A. 36.8 mg/L
C = 100e^(−1) ≈ 36.8. Linear decay would give 0 or 90; 10 confuses e^(−1) with 0.1.
What is the half-life of a first-order process with k = 0.1 per day?
C. 6.93 days
t½ = ln 2/k = 0.693/0.1 = 6.93 days.
What is the characteristic equation of y″ − 5y′ + 6y = 0, and what are its roots?
D. m² − 5m + 6 = 0; m = 2 and 3
Substitute e^(mx): m² − 5m + 6 = 0, roots 2 and 3, so y = Ae^(2x) + Be^(3x).
Which average is most appropriate for summarising log-normally distributed bacterial counts?
A. Geometric mean
Geometric means suit multiplicative, skewed data; regulations often use them for coliforms.
Adding an outlier of 30 to the data 4, 8, 6, 5, 7 changes the median from 6 to
B. 6.5
Ordered 4, 5, 6, 7, 8, 30: median = (6 + 7)/2 = 6.5; the mean jumps to 10, showing the median's robustness.
What does the central limit theorem state?
D. Means of large samples are near-normally distributed
The central limit theorem: whatever the parent distribution, means of sufficiently large samples are approximately normally distributed, with standard error σ/√n. It says nothing about the raw data themselves being normal.
What is the probability that a 100-year flood occurs at least once during a 50-year design life, assuming independent years?
D. About 39 per cent
R = 1 − 0.99⁵⁰ ≈ 0.39. 50% assumes linear accumulation; 1% is the annual probability.
What return period must a structure be designed for to keep the risk of exceedance to 10 per cent over a 50-year life?
C. About 475 years
Solve 1 − (1 − 1/T)⁵⁰ = 0.1: 1/T = 1 − 0.9^(1/50), T ≈ 475. 500 years is a rough rounding of 50/0.1; 50 equals the design life.
With slope 0.6, mean x = 3 and mean y = 4, what is the intercept of the regression line?
C. 2.2
a = ȳ − b x̄ = 4 − 1.8 = 2.2.
Why should regression predictions not be extrapolated far beyond the range of observed data?
A. The data do not support the fit there
A fitted regression is supported only within the range of the data; outside it the relationship may change form, so extrapolated predictions have no empirical basis. Software can compute them, which is exactly the danger.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Do these early in revision so they are fast on the day.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.