LAISHA
Open Laisha

State statistical services Statistical Quality Control & Reliability: practice questions

State statistical services: Statistical Officer / Assistant Statistical Officer (State PSCs and selection boards) · India · State Public Service Commissions and Subordinate Service Selection Boards

Original practice questions written to the published syllabus · not past papers
10worked here, free
84written to this exam in this subject
10syllabus units

About State statistical services

State statistical services: Statistical Officer / Assistant Statistical Officer (State PSCs and selection boards) is a government recruitment exam run by State Public Service Commissions and Subordinate Service Selection Boards, for candidates in India. Varies by state: usually an objective screening test in statistics and general studies, some with a descriptive paper and interview.

Official site: mospi.gov.in.

We have not been able to confirm these details against the exam body's own specification, so fees, dates and pass marks are left out on purpose. Check the current format, eligibility, fees and dates on the official site.

Statistical Quality Control & Reliability in State statistical services

Computations of control limits, interpretation of charts, and simple acceptance-sampling probabilities.

Monitoring and accepting quality: Shewhart charts for variables and attributes, CUSUM and EWMA charts, process capability, acceptance sampling plans with their OC, AOQ and ATI curves, and reliability models, applied to seed testing, food processing and input quality. The Agricultural Engineering track covers control charts briefly; this is the full subject.

Our 84 State statistical services questions in this subject: 22 easy, 44 medium, 18 hard, across 10 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to State statistical services and are not shown on any other exam's page.

Question 1 · easy

For subgroups of 5 with R̄ = 0.40 kg, D₃ = 0 and D₄ = 2.114. What is the R chart upper limit?

  1. 0.846 kg
  2. 1.20 kg
  3. 0.231 kg
  4. 0.400 kg
Answer and working

A. 0.846 kg

UCL = D₄R̄ = 2.114 × 0.40 = 0.846; LCL = 0.

Question 2 · easy

With R̄ = 0.40 kg from subgroups of 5 (d₂ = 2.326), what is σ̂?

  1. 0.179 kg
  2. 0.172 kg
  3. 0.400 kg
  4. 0.930 kg
Answer and working

B. 0.172 kg

σ̂ = R̄/d₂ = 0.40/2.326 = 0.172.

Question 3 · medium

With p̄ = 0.04, how large must n be for the p chart to have a positive lower limit?

  1. More than 100
  2. More than 9
  3. More than 216
  4. More than 25
Answer and working

C. More than 216

LCL > 0 requires p̄ > 3√[p̄(1 − p̄)/n], i.e. n > 9(1 − p̄)/p̄ = 216.

Question 4 · medium

An EWMA uses λ = 0.2 and L = 3. What are its steady-state limits?

  1. μ₀ ± 3σ
  2. μ₀ ± 0.2σ
  3. μ₀ ± σ
  4. μ₀ ± 0.6σ
Answer and working

C. μ₀ ± σ

Lσ√[λ/(2 − λ)] = 3σ√(0.2/1.8) = 3σ/3 = σ.

Question 5 · hard

An EWMA with λ = 0.2 starts at z₀ = 500. The next two observations are 503 and 501. What is z₂?

  1. 500.68
  2. 501.00
  3. 502.00
  4. 500.60
Answer and working

A. 500.68

z₁ = 0.2 × 503 + 0.8 × 500 = 500.60; z₂ = 0.2 × 501 + 0.8 × 500.60 = 500.68. 502 is the plain average of the two observations.

Question 6 · medium

A process is out of statistical control. What can be said about its capability index?

  1. It is not meaningful
  2. It equals Pp
  3. It is underestimated by exactly 30%
  4. It is always above 1
Answer and working

A. It is not meaningful

An unstable process has no single distribution to compare with specifications; stability comes first.

Question 7 · medium

What two points are commonly used to design a single sampling plan?

  1. (AQL, 1 − α) and (LTPD, β)
  2. (0, 1) and (1, 0)
  3. (AOQL, ATI) and (ASN, n)
  4. (Cp, Cpk) and (USL, LSL)
Answer and working

A. (AQL, 1 − α) and (LTPD, β)

Choose n and c so that P_a ≥ 1 − α at the AQL and P_a ≤ β at the LTPD.

Question 8 · easy

Three components with reliabilities 0.95, 0.98 and 0.99 are in series. What is the system reliability?

  1. 0.922
  2. 0.973
  3. 0.950
  4. 0.999990
Answer and working

A. 0.922

Series: product = 0.922. 0.999999 is the parallel arrangement.

Question 9 · medium

A pump with reliability 0.95 is duplicated in parallel. What is the reliability of the pump stage?

  1. 0.95
  2. 0.9975
  3. 0.9025
  4. 0.975
Answer and working

B. 0.9975

Parallel: 1 − (0.05)² = 0.9975; 0.9025 is the series value.

Question 10 · hard

In a Type II censored exponential life test with r failures and total time on test T, what is the distribution of 2T/θ?

  1. χ² with 2r degrees of freedom
  2. F with (r, 2r) df
  3. Normal with mean r
  4. χ² with r degrees of freedom
Answer and working

A. χ² with 2r degrees of freedom

T is a sum of r exponential spacings scaled by θ, giving gamma(r) and 2T/θ ~ χ²₂ᵣ, the basis of exact limits.

A study plan for Statistical Quality Control & Reliability in State statistical services

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (46% of the 84 questions): Control charts for variables: X-bar, R and s charts (11, 13%); OC, AOQ, AOQL, ASN and ATI curves (10, 12%); Acceptance sampling by attributes: single, double and sequential plans (9, 11%); Chance and assignable causes of variation (9, 11%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: CUSUM and EWMA charts (9, 11%); Reliability: hazard rate, series and parallel systems, life testing (9, 11%); Control charts for attributes: p, np, c and u charts (8, 10%); Acceptance sampling by variables (7, 8%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Process capability indices (7, 8%); Six Sigma and design for quality (introduction) (5, 6%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: OC, AOQ, AOQL, ASN and ATI curves (4 hard of 10), CUSUM and EWMA charts (3 hard of 9), Reliability: hazard rate, series and parallel systems, life testing (3 hard of 9).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Process capability indices (3 easy of 7); Control charts for attributes: p, np, c and u charts (3 easy of 8).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — State statistical services Statistical Quality Control & Reliability

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.