Original practice questions written to the published syllabus · not past papersNCEES PE Agricultural and Biological Engineering is a licensing and registration exam run by NCEES (ASABE is the content partner), for candidates in USA. Computer-based, 85 questions, 9.5-hour appointment (8.5 hours of exam). Once a year (next: 28 Oct 2026). Closed book with the electronic NCEES handbook and supplied searchable ASABE standards; SI and US customary units.
Source: ncees.org.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
Applied use of GIS and GNSS data in design: coordinate systems and datums, map scale and area, contributing area from DEMs, curve-number and erosion inputs from spatial data, and accuracy of GNSS positions and heights.
Mapping land and water from satellites and in GIS: images, indices, elevation models and watershed delineation.
Our 57 NCEES PE Agricultural and Biological Engineering questions in this subject: 16 easy, 31 medium, 10 hard, across 6 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to NCEES PE Agricultural and Biological Engineering and are not shown on any other exam's page.
Computing the mean slope of each sub-watershed from a slope raster and a sub-watershed raster is an example of which map algebra operation?
A. A zonal operation
Zonal operations summarise one layer within zones defined by another. Local operations work cell by cell; focal operations use a moving neighbourhood (slope itself is computed focally); global operations use the whole raster, such as Euclidean distance.
After intersecting a field-boundary layer with a soil-unit layer, many tiny thin polygons appear along boundaries that should coincide. What are they and how are they usually handled?
A. Sliver polygons; remove them with a cluster tolerance or by eliminating small polygons
Slivers arise when the same boundary was digitised separately in two layers and the lines do not exactly match; they are removed by snapping/cluster tolerances or merging polygons below a size threshold. They are not nodes, buffers or raster artefacts.
A flow accumulation raster from a 30 m DEM shows 5000 upstream cells at a proposed check-dam site. What is the contributing area?
C. 4.5 km²
Area = 5000 × 30 × 30 = 4,500,000 m² = 4.5 km² (450 ha). 0.15 km² multiplies by 30 m instead of 900 m²; 45 km² and 1.5 km² are unit or factor slips.
In the Strahler stream ordering system, a third-order stream begins where
A. two second-order streams join
Strahler order increases by one only when two streams of equal order meet: two second-order streams form a third-order stream. A second-order stream joined by a first-order stream stays second order; two first-order streams form a second-order stream.
Why does automated D8 delineation often fail in flat, canal-irrigated plains, and what is a common remedy?
B. Tiny height errors and artificial embankments dominate flow; burn in mapped drains and verify in the field
Where relief is less than DEM error, and embankments, roads and canals control flow, D8 directions become arbitrary; mapped drainage lines are burned into the DEM and results are checked by survey. Flat DEMs usually have many spurious sinks; D8 should be run in projected coordinates; raising the threshold does not fix wrong directions.
A receiver's clock is in error by 1 microsecond. What range error does this produce?
A. About 300 m
Range error = c × Δt = 3 × 10⁸ m/s × 1 × 10⁻⁶ s ≈ 300 m. 3 m corresponds to 10 ns; 30 km to 100 µs; 0.3 m to 1 ns.
A farm needs centimetre-level positioning for auto-steer tractors and laying subsurface drain lines. Which technique is appropriate?
C. RTK using carrier-phase corrections from a base or reference network
Real-time kinematic positioning resolves carrier-phase ambiguities and gives centimetre accuracy over baselines of up to a few tens of km. Autonomous positioning gives metres; SBAS and code DGNSS give sub-metre to metre accuracy, not enough for drain grades.
A basin has 24 first-order and 6 second-order streams. What is the bifurcation ratio between these orders?
B. 4.0
Rb = N1/N2 = 24/6 = 4.0. 0.25 inverts the ratio; 18 is the difference; 3.0 would need 18 first-order streams.
A GIS assigns curve number 80 to a sub-catchment. For a storm of 100 mm, what is the direct runoff by the SCS curve-number method with Ia = 0.2S?
D. 50.5 mm
S = 25,400/80 − 254 = 63.5 mm; Ia = 12.7 mm. Q = (100 − 12.7)²/(100 + 0.8 × 63.5) = 87.3²/150.8 = 50.5 mm. 46.6 mm uses (P + S) in the denominator; 63.5 mm is S itself; 80 mm reads the curve number as runoff.
Why should a raw data folder be kept separate from processed outputs in a GIS project?
A. So original data are never overwritten and every result can be traced back to its inputs
Keeping raw data untouched protects against accidental overwriting and supports reproducibility and audit. Folder structure does not affect loading speed, projection inheritance or file-size limits.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Do these early in revision so they are fast on the day.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.