Original practice questions written to the published syllabus · not past papersNCEES PE Agricultural and Biological Engineering is a licensing and registration exam run by NCEES (ASABE is the content partner), for candidates in USA. Computer-based, 85 questions, 9.5-hour appointment (8.5 hours of exam). Once a year (next: 28 Oct 2026). Closed book with the electronic NCEES handbook and supplied searchable ASABE standards; SI and US customary units.
Source: ncees.org.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
Applying supplied standards and code formulas: load combinations, beam moment and deflection for purlins and joists, timber and steel member checks, concrete beam and slab capacity, footing sizing from allowable bearing pressure, and structural loads on bins and livestock buildings. Expect multi-step numericals in US customary or SI units.
Materials, structural members, foundations and estimates for farm buildings and small works.
Our 23 NCEES PE Agricultural and Biological Engineering questions in this subject: 3 easy, 7 medium, 13 hard, across 8 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to NCEES PE Agricultural and Biological Engineering and are not shown on any other exam's page.
Under ASTM C150, which type of Portland cement is intended for high sulphate resistance?
C. Type V
ASTM C150: Type I general purpose, Type II moderate sulphate resistance, Type III high early strength, Type IV low heat of hydration, Type V high sulphate resistance (low C3A). Indian and European standards name sulphate-resisting cements differently.
Soil tests at the site of a dairy effluent sump show a high sulphate content. Which binder choice is most appropriate for the sump's concrete, subject to the local code?
B. A sulphate-resisting or slag/pozzolana blended cement, with a low water–cement ratio
Sulphate attack is driven by reaction of sulphates with C3A hydrates and calcium hydroxide; low-C3A (sulphate-resisting) or slag/pozzolana blended cements, plus low permeability (low w/c, good compaction and curing), resist it. Extra C3A makes attack worse, and rapid-hardening cement is usually high in C3A. Codes set the exact cement type and w/c for each sulphate class, and they differ by country.
Under the ACI 318 rule for f′c ≤ 35 MPa, the required average strength is the larger of f′c + 1.34 s and f′c + 2.33 s − 3.5 (MPa). For f′c = 28 MPa and s = 3.5 MPa, what is it?
D. 32.7 MPa
f′c + 1.34 s = 28 + 4.69 = 32.69; f′c + 2.33 s − 3.5 = 28 + 8.155 − 3.5 = 32.66. The larger is 32.7 MPa. 33.8 applies the Indian 1.65 s rule to an ACI problem; 36.2 forgets the − 3.5 term. 31.5 MPa adds only one standard deviation (28 + 3.5).
Why is bamboo generally unsuitable as a substitute for steel reinforcement in structural concrete?
C. It swells and shrinks with moisture, bonds weakly and has a low elastic modulus
Bamboo has high tensile strength (far above concrete's), but moisture movement breaks the bond, cracks the concrete, and the low modulus means large deflections; it is also prone to decay inside concrete. It is light, not heavy, and it does not form sulphates with cement.
What is the minimum longitudinal steel for a 300 × 500 mm RC column under IS 456?
B. 1200 mm²
IS 456 minimum is 0.8% of gross area: 0.008 × 150,000 = 1200 mm². 1500 mm² is ACI 318's 1% minimum; 6000 mm² is the 4% practical maximum; 600 mm² is half the requirement.
In a 15-year-old dairy shed, the RC columns show rust staining and spalled concrete for about 300 mm above the floor, while the upper parts are sound. What is the most likely cause and the sound repair approach?
D. Manure and wash water attacking the base; repair, treat the bars, restore cover, add a plinth
Damage confined to the wet zone at floor level points to corrosion driven by moisture and aggressive manure and cleaning water, not to overload (which would show cracking along the length or at heads) or settlement (which tilts or cracks walls and beams). Repair: break out unsound concrete, clean or replace bars, reinstate cover with a suitable repair mortar, and add a plinth or protective sleeve and drainage so the zone stays drier.
Roof trusses are spaced 4 m apart with panel points every 1.5 m along the plan. The roof load is 0.9 kN/m² of plan area. What load acts at each internal panel point?
B. 5.40 kN
Tributary area per internal panel point = 4 × 1.5 = 6 m²; load = 0.9 × 6 = 5.40 kN. Half of that (2.70 kN) acts at each end panel point. 3.60 kN omits the panel length; 1.35 kN omits the truss spacing.
A light open-sided machinery shed has steel trusses with sheet roofing. Under design wind, the roof suction exceeds the dead load. What must the designer check?
B. Force reversal in members and the hold-down of trusses against uplift
Net uplift reverses the sign of member forces: the bottom chord, normally in tension, goes into compression and may buckle over its long unbraced length, and the supports must resist pull-out. Wind can act downward on some roof zones but uplift on light roofs is often critical; sheeting fixings, purlins, trusses, columns and foundations all lie on the uplift load path.
A simply supported parallel-chord truss spans 12 m with a depth of 2 m between chord centrelines. A single 60 kN load acts at the midspan bottom joint. Using the method of sections, what is the force in the bottom chord at midspan?
B. 90 kN tension
Reactions = 30 kN each. Cut at midspan and take moments about the top joint above the cut: M = 30 × 6 = 180 kN·m = force × depth, so force = 180/2 = 90 kN. The bottom chord of a simply supported truss under gravity is in tension, so compression is wrong in sign; 180 kN forgets to divide by the depth.
A farmer-producer company wants a working 500-tonne cold store delivered by one firm that will design, build, commission and hand it over. Which procurement route matches this?
B. A turnkey, EPC or design–build contract with a single point of responsibility
Turnkey/EPC contracts put design, construction and commissioning with one contractor, who hands over a functioning facility; FIDIC's Silver Book is an international example. Item-rate and percentage-rate contracts presume the owner has completed the design.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Do these early in revision so they are fast on the day.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.