NCEES PE Agricultural and Biological Engineering · USA · NCEES (ASABE is the content partner)
Original practice questions written to the published syllabus · not past papersNCEES PE Agricultural and Biological Engineering is a licensing and registration exam run by NCEES (ASABE is the content partner), for candidates in USA. Computer-based, 85 questions, 9.5-hour appointment (8.5 hours of exam). Once a year (next: 28 Oct 2026). Closed book with the electronic NCEES handbook and supplied searchable ASABE standards; SI and US customary units.
Source: ncees.org.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
Graphics, CAD and GIS appear under Common System Applications. Expect to interpret drawings and plans rather than draw: reading orthographic and sectional views, scales on plans, dimensioning and tolerance stack-up, limits and fits, weld symbols in the AWS convention, and the use of CAD models for quantities and checks. Third-angle projection and ASME Y14.5 conventions are the US default.
Reading and making drawings of machine parts and buildings, by hand and in CAD.
Our 38 NCEES PE Agricultural and Biological Engineering questions in this subject: 3 easy, 15 medium, 20 hard, across 7 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to NCEES PE Agricultural and Biological Engineering and are not shown on any other exam's page.
The end projectors of a line are 40 mm apart along XY. In the front view the ends differ in height by 30 mm, and in the top view they differ in distance from the VP by 50 mm. What is the true length of the line?
B. 70.7 mm
The three differences are mutually perpendicular, so TL = √(40² + 30² + 50²) = √5000 = 70.7 mm. 64.0 mm is only the top-view length and 50.0 mm only the front-view length; 120 mm adds the components arithmetically.
On a shaft drawing, the overall length of 200 mm is shown in parentheses as (200), while the individual step lengths are dimensioned and toleranced. What does the parenthesised dimension mean?
D. An auxiliary dimension, for information only and not toleranced
Parentheses mark an auxiliary (reference) dimension, which duplicates information derivable from other dimensions and carries no tolerance. A theoretically exact dimension is shown in a rectangular box, not in parentheses.
A hole is 25.000–25.021 mm and its shaft is 24.980–24.993 mm. What are the maximum and minimum clearances?
A. 0.041 mm and 0.007 mm
Maximum clearance = largest hole − smallest shaft = 25.021 − 24.980 = 0.041 mm. Minimum clearance = smallest hole − largest shaft = 25.000 − 24.993 = 0.007 mm. Pairing largest with largest or smallest with smallest gives intermediate values, not the extremes. Both clearances are positive, so this is a clearance fit. Largest hole − largest shaft gives 0.028 mm, and smallest hole − smallest shaft gives 0.020 mm.
A hole is 30.000–30.021 mm and a shaft is 30.002–30.015 mm. Classify the fit and give its extreme values.
D. Transition; maximum clearance 0.019 mm, maximum interference 0.015 mm
Largest hole − smallest shaft = 30.021 − 30.002 = +0.019 mm (clearance possible). Smallest hole − largest shaft = 30.000 − 30.015 = −0.015 mm (interference possible). Either can occur, so it is a transition fit. Calling it a clearance fit ignores that the largest shaft exceeds the smallest hole.
Why is the hole-basis system of fits more common than the shaft-basis system in general machine work?
A. Holes are made with fixed-size reamers and plug gauges, so fixing hole limits saves tooling
Keeping the hole at H means a small set of reamers and gauges serves many fits, while shafts are easily turned or ground to any size. The shaft-basis system is permitted and is used, for example, when one drawn shaft carries several parts with different fits.
In an isometric drawing, an engineer measures a line parallel to one of the axes and finds it to be 40 mm, but the line is not drawn to the isometric scale. What true length does it represent?
D. 40 mm, because an isometric drawing uses true lengths along the axes
An isometric drawing (as opposed to projection) is drawn with full lengths on isometric lines, so an isometric line of 40 mm represents 40 mm. Only non-isometric lines cannot be measured. Correcting by 0.816 would apply only to an isometric projection.
For a hole of size 10.0–10.2 mm with a position tolerance of ⌀0.1 at MMC, what is the virtual condition, i.e. the largest fixed pin that will always pass through?
A. 9.9 mm
Virtual condition of an internal feature at MMC = MMC − geometric tolerance = 10.0 − 0.1 = 9.9 mm. 10.1 mm adds the tolerance as for an external feature; 10.0 mm ignores the position error. 10.3 mm adds the tolerance to the largest hole size.
Under the 3-2-1 principle, how many points of contact establish the primary, secondary and tertiary datums?
D. Three, two and one
The primary datum plane is set by three points, the secondary by two and the tertiary by one, removing all six degrees of freedom. Reversing the order would leave the part unstable on its primary face.
On a weld symbol, a small circle is drawn where the arrow line meets the reference line, together with a fillet triangle. What does it mean?
B. Fillet weld all round the joint, as for a tube welded to a plate
The circle at the junction means weld all round. A field weld uses a flag; flush finishing uses a contour symbol; a spot weld has its own circular elementary symbol placed on the reference line.
A datum feature symbol is attached to the large flat face on which a gearbox cover seats. Why is this face usually chosen as the primary datum?
D. It is the functional seating face that locates the part in assembly
Datums should reflect function: the seating face establishes the plane on which the part sits. Size, paint or finish do not decide datum choice, although a functional face is often also large and machined.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Do these early in revision so they are fast on the day.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.