NCEES PE Agricultural and Biological Engineering Electrical Machines & Power Utilisation: practice questions

NCEES PE Agricultural and Biological Engineering · USA · NCEES (ASABE is the content partner)

Original practice questions written to the published syllabus · not past papers
10worked here, free
29written to this exam in this subject
9syllabus units

About NCEES PE Agricultural and Biological Engineering

NCEES PE Agricultural and Biological Engineering is a licensing and registration exam run by NCEES (ASABE is the content partner), for candidates in USA. Computer-based, 85 questions, 9.5-hour appointment (8.5 hours of exam). Once a year (next: 28 Oct 2026). Closed book with the electronic NCEES handbook and supplied searchable ASABE standards; SI and US customary units.

Source: ncees.org.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Electrical Machines & Power Utilisation in NCEES PE Agricultural and Biological Engineering

Electric motors under Common System Applications: motor input power and current from pump and fan duty, selecting a standard motor size, efficiency and wire-to-water efficiency, energy cost, VFD savings with the affinity laws, capacitor sizing for power-factor correction, and conductor sizing for voltage drop on long farm runs. Equipotential planes (ASABE EP473) appear under facilities.

Motors and power supply on farms and in processing plants: choosing, starting, protecting and paying for electric drives.

Our 29 NCEES PE Agricultural and Biological Engineering questions in this subject: 1 easy, 8 medium, 20 hard, across 9 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to NCEES PE Agricultural and Biological Engineering and are not shown on any other exam's page.

Question 1 · hard

A 25 kVA transformer (iron loss 110 W, full-load copper loss 500 W) supplies pumps at 25 kVA for 8 h, a 5 kW unity power-factor load for 6 h, and no load for 10 h each day. The 25 kVA load is at 0.8 power factor. What is the all-day efficiency?

  1. 97.11 %
  2. 96.56 %
  3. 97.04 %
  4. 95.17 %
Answer and working

B. 96.56 %

Output energy = 20 kW × 8 h + 5 kW × 6 h = 190 kWh. Iron loss runs all 24 h: 0.11 × 24 = 2.64 kWh. Copper loss = 0.5 × 8 × 1² + 0.5 × 6 × (5/25)² = 4.12 kWh. η = 190/(190 + 2.64 + 4.12) = 96.56 %. 97.11 % counts iron loss only during the 14 loaded hours. 95.17 % charges full-load copper loss for all 14 hours. 97.04 % is the full-load efficiency, not the all-day figure.

Question 2 · medium

A three-phase, 400 V, 7.5 kW (output) pump motor has full-load efficiency 0.88 and power factor 0.85. What is its full-load line current?

  1. 10.8 A
  2. 8.1 A
  3. 14.5 A
  4. 25.1 A
Answer and working

C. 14.5 A

I = P_out/(√3 V η pf) = 7500/(1.732 × 400 × 0.88 × 0.85) = 14.5 A. 10.8 A ignores efficiency and power factor. 25.1 A omits √3. 8.1 A multiplies by η and pf instead of dividing.

Question 3 · medium

A pump motor will be installed at a hill farm 2500 m above sea level. Why may it need to be derated?

  1. Thinner air cools it less well than at the 1000 m reference altitude
  2. Lower air pressure raises the supply frequency the motor receives
  3. Higher altitude raises insulation class and so its permitted current
  4. Lower air density increases the slip and so the synchronous speed
Answer and working

A. Thinner air cools it less well than at the 1000 m reference altitude

IEC 60034-1 rates motors for altitudes up to 1000 m and coolant up to 40 °C. Above that, the air's lower density reduces heat removal, so output is derated per the manufacturer's table. Altitude does not change frequency, insulation class or synchronous speed.

Question 4 · medium

A motor nameplate shows a NEMA service factor of 1.15. What does that mean?

  1. It can run at 115 % of synchronous speed when fed from a variable-frequency drive
  2. It can deliver 115 % of rated power continuously at rated voltage and frequency, running hotter
  3. It may draw 115 % of rated current for one minute in every hour of operation before its overload relay trips
  4. Its full-load efficiency is 115 % of the minimum value required by the national standard
Answer and working

B. It can deliver 115 % of rated power continuously at rated voltage and frequency, running hotter

Service factor is a continuous overload margin at rated voltage and frequency, at the cost of higher temperature and shorter insulation life; it is not a design basis. It is not a timed overcurrent allowance, an efficiency rating or a speed limit.

Question 5 · hard

A dairy installs several diode-front-end VFDs on its milk vacuum pumps and fans. What supply-quality effect should the engineer plan for?

  1. Reverse power flow into the grid whenever the motors run at full speed
  2. A rise in supply frequency whenever the drives reduce motor speed
  3. Harmonic currents that distort voltage and heat transformers and cables
  4. A fall in displacement power factor to about 0.5 lagging whenever they run at full load
Answer and working

C. Harmonic currents that distort voltage and heat transformers and cables

Diode-rectifier drives draw pulsed current rich in 5th, 7th, 11th and 13th harmonics; line reactors, DC chokes or filters reduce them, and capacitor banks must be detuned. Their displacement power factor is close to unity, they cannot change supply frequency, and they do not export power when motoring.

Question 6 · hard

Line copper losses supplying an irrigation load are 2 kW at 0.7 power factor. If power factor is raised to 0.95 with the same real power and voltage, what do the losses become?

  1. 1.47 kW
  2. 2.00 kW
  3. 3.68 kW
  4. 1.09 kW
Answer and working

D. 1.09 kW

Losses ∝ I² ∝ 1/pf², so new losses = 2 × (0.7/0.95)² = 1.09 kW. 1.47 kW scales linearly with current. 3.68 kW inverts the ratio. 2.00 kW assumes power factor has no effect on losses.

Question 7 · hard

A 15 kVAR, 400 V, 50 Hz capacitor bank is delta-connected. What capacitance is needed in each phase?

  1. 99.5 µF
  2. 625.0 µF
  3. 298.4 µF
  4. 33.2 µF
Answer and working

A. 99.5 µF

Each delta capacitor sees 400 V and supplies 5 kVAR: C = Q/(3ωV²) = 15000/(3 × 314.16 × 400²) = 99.5 µF. 298.4 µF is the star-connected value (only 231 V per capacitor). 33.2 µF divides by 3 twice. 625.0 µF uses f = 50 instead of ω = 2πf.

Question 8 · hard

A solar pump must deliver 50 m³ a day against a total dynamic head of 40 m. Motor-pump subsystem efficiency is 0.45, the design month has 5.5 peak sun hours, and a derating factor of 0.8 covers temperature, dust and wiring. What PV array size is needed?

  1. 0.56 kWp
  2. 2.20 kWp
  3. 0.99 kWp
  4. 2.75 kWp
Answer and working

D. 2.75 kWp

Hydraulic energy = 1000 × 9.81 × 50 × 40 J = 19.62 MJ = 5.45 kWh. Array = 5.45/(0.45 × 5.5 × 0.8) = 2.75 kWp. 0.99 kWp ignores both efficiency and derating. 2.20 kWp omits the derating. 0.56 kWp multiplies by efficiency instead of dividing.

Question 9 · hard

A three-phase 400 V borewell motor draws 14.47 A at 0.85 power factor through 100 m of copper cable (resistivity 0.0175 Ω·mm²/m). Reactance is neglected and voltage drop is limited to 3 % (12 V). What minimum conductor cross-section is needed?

  1. 3.66 mm²
  2. 3.11 mm²
  3. 3.59 mm²
  4. 6.21 mm²
Answer and working

B. 3.11 mm²

ΔV = √3·I·(ρL/A)·cos φ, so A = √3 × 14.47 × 100 × 0.0175 × 0.85/12 = 3.11 mm²; choose the next standard size (4 mm²) and check current capacity. 3.59 mm² uses the single-phase factor 2. 3.66 mm² ignores power factor. 6.21 mm² doubles the length, which is only right for single-phase loop length.

Question 10 · medium

Dairy cows in a milking parlour hesitate to enter and let down milk poorly, and small voltages are measured between the feed rail and the wet floor. What is the recommended remedy?

  1. Insulate the floor with rubber mats over the concrete
  2. Install an equipotential plane bonded to the metal fittings
  3. Fit a larger overload relay to the vacuum pump starter
  4. Change all parlour motors from three-phase to single-phase
Answer and working

B. Install an equipotential plane bonded to the metal fittings

Stray voltage between metalwork and floor drives current through animals, which are more sensitive than people. A bonded equipotential plane (ASABE EP473) keeps everything the animal touches at the same potential. Overload relays and motor phase do not address it, and mats wear and do not equalise potential.

A study plan for Electrical Machines & Power Utilisation in NCEES PE Agricultural and Biological Engineering

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (45% of the 29 questions): Selecting motors for pumps, threshers and processing machines (5, 17%); Power factor correction (4, 14%); Three-phase induction motors: slip and torque-speed curve (4, 14%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Variable-frequency drives (4, 14%); Rural power distribution and tariffs (3, 10%); Transformers in practice (3, 10%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Wiring and protection: fuses, MCB, ELCB and earthing (3, 10%); Motor starters (2, 7%); DC machines (1, 3%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Power factor correction (4 hard of 4), Rural power distribution and tariffs (3 hard of 3), Motor starters (2 hard of 2).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Three-phase induction motors: slip and torque-speed curve (1 easy of 4).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — NCEES PE Agricultural and Biological Engineering Electrical Machines & Power Utilisation

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.