Original practice questions written to the published syllabus · not past papersTamil Nadu PSC — Agricultural Engineering (Code 164, degree standard) is a government recruitment exam run by Tamil Nadu Public Service Commission, for candidates in India. Degree-standard subject paper (for posts such as Assistant Engineer (Agri)).
Source: tnpsc.gov.in.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
Estimating erosion and designing the bunds, terraces, waterways, spillways, ponds and dams that control it.
Our 51 Tamil Nadu PSC questions in this subject: 25 easy, 22 medium, 4 hard, across 13 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to Tamil Nadu PSC and are not shown on any other exam's page.
The three phases of every water erosion event, in order, are:
C. detachment, transport and deposition
Soil must first be detached (by raindrop impact or flow shear), then transported by runoff, then deposited where the flow slows. Splash, sheet and gully are forms of erosion, not phases.
Vetiver grass is widely used in soil conservation mainly as:
B. a dense, deep-rooted contour hedge that slows runoff and traps sediment
Vetiver forms a stiff, dense hedge along the contour; sediment deposits behind it and natural terraces form over time. It is not a shelterbelt tree or a green manure crop.
Using VI = 0.3(S/3 + 2), with S in percent, the vertical interval between contour bunds on a 6% slope is:
D. 1.2 m
VI = 0.3 × (6/3 + 2) = 0.3 × 4 = 1.2 m. Forgetting to divide S by 3 gives 2.4; forgetting the 0.3 gives 4.0. Dropping the S/3 term gives 0.3 × 2 = 0.6 m.
Surplus arrangements such as waste weirs are provided in contour bunds to:
B. let runoff in excess of the design storage pass safely without breaching the bund
A bund stores only the design runoff. Waste weirs at low points or ends pass the excess in a controlled way; without them water overtops at the weakest point and breaches the bund.
In the field, contour bund alignments are best located using:
A. a levelling instrument to peg points of equal elevation, then smoothing sharp bends
A contour is a line of equal elevation, so it must be pegged with a level (dumpy level, total station or a simple water-tube or A-frame level). Sharp bends are eased into curves so implements can follow them.
For level bench terraces with vertical risers and a vertical interval of 1.2 m, the earthwork (cut) per hectare is:
C. 1,500 m³
Length of terrace per ha = 10,000/W; cut per metre = W·VI/8; so cut per ha = 10,000 × VI/8 = 1,250 × VI = 1,500 m³, independent of W. 3,000 m³ double-counts fill; 6,000 m³ uses the whole triangle under the original slope (W·VI/2 per metre). 1,042 m³ divides 1,250 by VI instead of multiplying.
On a 20% slope the soil is deep enough to allow at most 0.5 m of cut at the inner edge of a level bench (vertical risers, balanced cut and fill). The widest bench that can be built without cutting below this depth is:
A. 5.0 m
For a balanced level bench, the cut at the inner edge is VI/2. Cut ≤ 0.5 m gives VI ≤ 1.0 m. W = 100 VI/S = 100 × 1.0/20 = 5.0 m. Treating 0.5 m as the VI gives 2.5 m, an unnecessarily narrow bench. 0.2 m multiplies VI by S/100 instead of dividing.
The usual order of the four stages of gully development is:
C. formation, development, healing, stabilisation
A gully first forms by scour of the topsoil, then enlarges and advances its head (most active stage), then vegetation begins to establish (healing), and finally the gully stabilises with a stable gradient and cover.
A dugout farm pond is 30 m × 30 m at the top, 3 m deep, with side slopes of 1.5:1 on all sides. By the prismoidal formula, its capacity is closest to:
A. 1,971 m³
Bottom side = 30 − 2 × 1.5 × 3 = 21 m; mid-depth side = 30 − 1.5 × 3 = 25.5 m. V = (d/6)(A1 + 4Am + A2) = 0.5 × (900 + 4 × 650.25 + 441) = 1,971 m³. The average-end-area formula gives 2,012 m³, an overestimate; the top area times depth ignores the sloping sides. Top area times depth gives 2,700 m³, and bottom area times depth gives 1,323 m³.
Wind strip cropping controls erosion mainly by:
D. reducing the unsheltered distance along the wind with alternate strips of erosion-resistant crops
Strips of resistant crops laid across the wind break the field into short lengths, so soil flow cannot build up by avalanching. In the WEQ this reduces L.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Do these early in revision so they are fast on the day.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.