About GATE

GATE — Agricultural Engineering (AG) is a postgraduate admission exam run by IITs and IISc on rotation (2027: IIT Madras), for candidates in India. Computer-based, 3 hours, 100 marks (15 General Aptitude + 85 technical: 25 one-mark and 30 two-mark questions). MCQ, MSQ and NAT; negative marking on MCQ only (−1/3 for one-mark, −2/3 for two-mark); no partial credit on MSQ. On-screen virtual calculator.

Source: gate2027.iitm.ac.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Soil & Water Conservation Engineering in GATE

Section 4 Soil and Water Erosion as short numericals, often numerical-answer type: the effect of changing slope length or steepness in the USLE, VI and HI of bunds and terraces, bench-terrace earthwork, grassed waterway velocity and dimensions with Manning's equation, weir capacity of drop spillways, check-dam spacing, flow-net seepage through embankments, and shelterbelt protected distance and wind transport modes.

Estimating erosion and designing the bunds, terraces, waterways, spillways, ponds and dams that control it.

Our 49 GATE questions in this subject: 3 easy, 25 medium, 21 hard, across 13 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to GATE and are not shown on any other exam's page.

Question 1 · medium

A storm has two uniform-intensity parts: 20 mm at 40 mm/h (30 minutes) followed by 10 mm at 10 mm/h (60 minutes). With e = 0.119 + 0.0873 log10 I (MJ/ha/mm), the storm's EI30 is closest to:

  1. 144.8 MJ·mm/(ha·h)
  2. 7.24 MJ·mm/(ha·h)
  3. 289.6 MJ·mm/(ha·h)
  4. 310.6 MJ·mm/(ha·h)
Answer and working

C. 289.6 MJ·mm/(ha·h)

Energy of part 1 = 20 × (0.119 + 0.0873 log10 40) = 5.177; part 2 = 10 × (0.119 + 0.0873 log10 10) = 2.063; E = 7.240 MJ/ha. The wettest 30 minutes delivered 20 mm, so I30 = 40 mm/h. EI30 = 7.240 × 40 = 289.6. Using the storm average intensity (20 mm/h) gives 144.8, treating all 30 mm as falling at 40 mm/h gives 7.766 × 40 = 310.6, and stopping at E gives 7.24.

Question 2 · medium

A sediment rating curve for a stream is Qs = 2 Q^1.5, with Qs in t/day and Q in m³/s. The sediment discharge at a flow of 16 m³/s is:

  1. 128 t/day
  2. 181 t/day
  3. 48 t/day
  4. 8 t/day
Answer and working

A. 128 t/day

Qs = 2 × 16^1.5 = 2 × 64 = 128 t/day. Multiplying by 1.5 instead of raising to the power gives 48; raising (2 × 16) to 1.5 gives 181. Using the power 0.5 gives 2 × 4 = 8 t/day.

Question 3 · medium

A terrace system on a 5% slope is spaced with VI = 0.305(XS + Y) m, using X = 0.6 and Y = 2. The horizontal spacing is closest to:

  1. 1.52 m
  2. 100 m
  3. 18.3 m
  4. 30.5 m
Answer and working

D. 30.5 m

VI = 0.305 × (0.6 × 5 + 2) = 0.305 × 5 = 1.525 m. HI = 100 × 1.525/5 = 30.5 m. Forgetting the 0.305 foot-to-metre factor gives 100 m; forgetting Y gives 18.3 m. 1.52 m is the vertical interval, not the horizontal spacing.

Question 4 · medium

For level bench terraces 6 m wide with a vertical interval of 1.2 m (cut and fill balanced), the volume of earth cut per 100 m length of terrace is:

  1. 180 m³
  2. 360 m³
  3. 720 m³
  4. 90 m³
Answer and working

D. 90 m³

Cut is a triangle of base W/2 and height VI/2: ½ × 3 × 0.6 = 0.9 m² = W·VI/8. Per 100 m: 90 m³. W·VI/4 counts cut plus fill (180 m³); W·VI/2 is the whole triangle under the original slope. W·VI/2 per metre gives 360 m³, and W·VI per metre gives 720 m³.

Question 5 · hard

Bench terraces 6 m wide on a 20% slope have earthen risers at 1:1 and a vertical interval of 1.5 m. The fraction of land occupied by the risers is:

  1. 25%
  2. 20%
  3. 10%
  4. 7.5%
Answer and working

B. 20%

Horizontal spacing = 100 VI/S = 100 × 1.5/20 = 7.5 m = bench 6 m + riser width. Riser horizontal width = U × VI = 1 × 1.5 = 1.5 m. Fraction = 1.5/7.5 = 20%. Dividing by the bench width alone gives 25%.

Question 6 · medium

Check dams with an effective height of 0.9 m are placed in a gully with a bed slope of 6%, using the head-to-toe rule. The spacing between dams is:

  1. 5.4 m
  2. 15 m
  3. 1.5 m
  4. 0.15 m
Answer and working

B. 15 m

Head-to-toe: L = H / S = 0.9/0.06 = 15 m, so the crest of each dam is level with the toe of the next one upstream. Using S = 6 gives 0.15 m. H × S (0.9 × 6) gives 5.4 m, and reading 6% as 0.6 gives 1.5 m.

Question 7 · hard

A straight drop spillway discharges 1.5 m³/s per metre of crest over a drop of 2.0 m. Using the drop number D = q²/(g h³) and Rand's relation L_d = 4.30 h D^0.27, the distance from the drop wall to where the nappe strikes the apron is closest to:

  1. 0.247 m
  2. 3.30 m
  3. 2.95 m
  4. 1.65 m
Answer and working

B. 3.30 m

D = 1.5²/(9.81 × 2³) = 2.25/78.48 = 0.0287. D^0.27 = 0.3833. L_d = 4.30 × 2.0 × 0.3833 = 3.30 m. Omitting h gives 1.65 m; using q instead of q² in D gives 2.95 m. Dropping the 0.27 exponent gives 4.30 × 2.0 × 0.0287 = 0.247 m.

Question 8 · hard

A pond must collect 4,000 m³ of runoff in a season with 500 mm of rain. If the seasonal runoff coefficient of the catchment is 0.2, the catchment area required is:

  1. 4 ha
  2. 0.8 ha
  3. 0.004 ha
  4. 0.16 ha
Answer and working

A. 4 ha

Runoff depth = 0.2 × 0.5 m = 0.1 m. Area = 4,000/0.1 = 40,000 m² = 4 ha. Forgetting the runoff coefficient gives 0.8 ha; using rainfall in mm without converting gives a tiny area. Working in mm without converting gives 40 m² = 0.004 ha, and multiplying by the coefficient gives 0.16 ha.

Question 9 · medium

Wind speed measured 2 m above a bare field is 8 m/s. The roughness length is 0.01 m and κ = 0.4. From the logarithmic profile u = (u*/κ) ln(z/z0), the friction velocity is closest to:

  1. 3.2 m/s
  2. 3.77 m/s
  3. 0.604 m/s
  4. 1.39 m/s
Answer and working

C. 0.604 m/s

u* = κ u / ln(z/z0) = 0.4 × 8 / ln 200 = 3.2/5.298 = 0.604 m/s. Using log10 gives 1.39; inverting κ gives 3.77.

Question 10 · easy

A shelterbelt is 12 m tall. If effective leeward protection is taken to extend 20 times the barrier height, the protected distance downwind is:

  1. 120 m
  2. 240 m
  3. 60 m
  4. 32 m
Answer and working

B. 240 m

Protected distance = 20 H = 20 × 12 = 240 m. 5 H (60 m) is closer to the windward-side effect; 10 H (120 m) is the zone of greatest reduction. 32 m adds 20 to the height.

A study plan for Soil & Water Conservation Engineering in GATE

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (55% of the 49 questions): Grassed waterways (7, 14%); Soil loss estimation: USLE, RUSLE and MUSLE (6, 12%); Bench and broad-base terraces (5, 10%); Drop, drop-inlet and chute spillways (5, 10%); Contour and graded bunds (4, 8%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Earthen dams: seepage and stability (4, 8%); Wind erosion mechanics (4, 8%); Farm ponds (3, 6%); Mechanics of water erosion (3, 6%); Sediment yield (3, 6%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Gully control (2, 4%); Wind erosion control and shelterbelts (2, 4%); Agronomic and biological conservation measures (1, 2%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Drop, drop-inlet and chute spillways (4 hard of 5), Earthen dams: seepage and stability (3 hard of 4), Farm ponds (2 hard of 3).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Wind erosion mechanics (2 easy of 4); Wind erosion control and shelterbelts (1 easy of 2).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — GATE Soil & Water Conservation Engineering

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.