Original practice questions written to the published syllabus · not past papersTamil Nadu PSC — Agricultural Engineering (Code 164, degree standard) is a government recruitment exam run by Tamil Nadu Public Service Commission, for candidates in India. Degree-standard subject paper (for posts such as Assistant Engineer (Agri)).
Source: tnpsc.gov.in.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
How much water a crop needs, when to give it, how to measure and convey it, and how to design surface irrigation.
Our 50 Tamil Nadu PSC questions in this subject: 28 easy, 21 medium, 1 hard, across 14 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to Tamil Nadu PSC and are not shown on any other exam's page.
Which set describes the FAO-56 hypothetical reference crop?
B. Grass 0.12 m tall, resistance 70 s/m, albedo 0.23
FAO-56 defines the reference as hypothetical grass, 0.12 m tall, rs = 70 s/m, albedo 0.23. The alfalfa option describes a tall reference (ASCE), and the others describe open water or an unrealistic surface.
Before irrigation a soil holds 18 % water by mass; field capacity is 28 % by mass, bulk density 1.4 g/cm³ and root depth 60 cm. If application efficiency is 70 %, what gross depth should be applied?
D. 120 mm
Net depth = (0.28 − 0.18) × 1.4 × 600 mm = 84 mm; gross = 84/0.70 = 120 mm. 84 mm is the net depth; 85.7 mm forgets bulk density; 58.8 mm multiplies by efficiency.
The mean diameter of bed sediment is 0.36 mm. What is Lacey's silt factor?
B. 1.06
f = 1.76 √d = 1.76 × √0.36 = 1.76 × 0.6 = 1.06 (d in mm). 0.63 forgets the square root; 2.93 divides; 0.80 takes the root of the product.
Apart from reducing seepage, which is a direct hydraulic benefit of lining a canal?
C. A smaller section carries the same flow
A smooth lining lowers n and permits higher velocities, so a smaller section carries the same flow. Lining reduces, not raises, waterlogging, and increased infiltration is the opposite of its purpose.
A graded border is best described as:
C. A long strip bounded by dikes, sloping along its length with no cross slope
Borders are strips with a longitudinal slope and zero cross slope so the sheet of water spreads evenly across. The level enclosed area is a basin, row channels are furrows, and the pipe describes drip.
With the same available stream size, how should basin size change from a clay to a sandy loam?
C. Smaller on the sandy loam
On high-intake soil water infiltrates quickly, so a small basin is needed to cover it before too much soaks in near the inlet. Fine soils allow larger basins for the same stream.
A canal diverts 1.0 m³/s at the head; 0.70 m³/s reaches the fields, and 0.49 m³/s is stored in the root zone. What is the field application efficiency?
D. 70 %
Application efficiency = water stored in root zone / water delivered to the field = 0.49/0.70 = 70 %. 49 % is the overall (conveyance × application) efficiency; 143 % inverts the ratio; 30 % is the conveyance loss fraction.
Which two losses reduce field application efficiency in surface irrigation?
B. Surface runoff (tailwater) and deep percolation below the root zone
Application efficiency is measured from the field inlet to the root zone, so its losses are runoff and deep percolation. Canal seepage lowers conveyance efficiency; transpiration is the beneficial use.
A distributary has a culturable command area of 20,000 ha. The intensity of irrigation in the peak season is 60 % and the duty at its head is 1,500 ha/cumec. What discharge must it carry?
B. 8.0 m³/s
Irrigated area = 0.60 × 20,000 = 12,000 ha; Q = 12,000 / 1,500 = 8.0 m³/s. 13.3 ignores intensity; 0.8 is a decimal slip; 4.8 applies intensity twice.
Warabandi, practised in the Indus basin of north-west India and Pakistan, is:
B. A fixed weekly rotation giving each farmer the full outlet flow for a time proportional to landholding
Under warabandi, each farmer on an outlet gets a fixed day and time slot each week, its length proportional to area. It is equitable and simple but not responsive to crop need. The other options describe demand, continuous or market delivery.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Do these early in revision so they are fast on the day.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.