About Agricultural and Biosystems Engineers Licensure Examination

Agricultural and Biosystems Engineers Licensure Examination (ABELE) is a licensing and registration exam run by Professional Regulatory Board of Agricultural and Biosystems Engineering, PRC, for candidates in Philippines. Paper-based, 2 days (Day 1 6 hours; Day 2 5 hours + 4 hours). Non-programmable calculator only; the Dec 2025 programme bans the Casio fx-991ES/ES Plus by name.

Source: prc.gov.ph.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Agricultural Structures & Environmental Control in Agricultural and Biosystems Engineers Licensure Examination

Structures, environment and bioprocess (36% bundle): livestock and poultry housing design, space requirements, ventilation and evaporative cooling, storage structures, and PAES standards for agricultural buildings.

Planning a farmstead and designing its buildings, stores and animal houses, including the ventilation that keeps animals healthy.

Our 38 Agricultural and Biosystems Engineers Licensure Examination questions in this subject: 5 easy, 17 medium, 16 hard, across 13 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to Agricultural and Biosystems Engineers Licensure Examination and are not shown on any other exam's page.

Question 1 · hard

A farm is planning a dairy unit beside an existing feed store. The milk tanker, feed deliveries, manure spreaders and dead-stock collection all use one track through the cow yards. What is the main planning fault?

  1. The track is too short, because milk tankers need at least a 1 km approach road
  2. Feed deliveries should pass through the cow yards so that cows can see the feed
  3. Clean and dirty traffic share one route, creating a biosecurity and hygiene risk
  4. Dead-stock collection should be inside the milking parlour for the driver's convenience
Answer and working

C. Clean and dirty traffic share one route, creating a biosecurity and hygiene risk

Good layout separates clean traffic (feed, milk) from dirty traffic (manure, dead stock) and keeps outside vehicles at the edge of the unit. Dead-stock collection belongs at the perimeter, never in the parlour, and there is no rule of a minimum approach length.

Question 2 · hard

The design wind speed is 35 m/s (q = 0.613V² Pa). A roof panel of tributary area 2.4 m × 6.0 m has a net uplift coefficient of 0.9. What is the uplift force on it?

  1. 9.73 kN
  2. 10.81 kN
  3. 0.28 kN
  4. 5.68 kN
Answer and working

A. 9.73 kN

q = 0.613 × 35² = 751 Pa; F = 0.9 × 751 × 14.4 m² = 9732 N ≈ 9.73 kN. Ignoring the coefficient gives 10.81 kN; using V instead of V² gives 0.28 kN; adding the sides instead of multiplying gives 5.68 kN.

Question 3 · hard

Why is a high eave or roof height recommended for naturally ventilated dairy sheds in hot climates?

  1. It lets the shed hold more hay above the cows, which insulates them from the sun
  2. It reduces wind flow through the shed, which otherwise chills the cows in summer
  3. It boosts the stack effect and moves the hot roof away from the cows
  4. Taller roofs collect less dust, so the cows' respiratory health improves directly
Answer and working

C. It boosts the stack effect and moves the hot roof away from the cows

Height between inlet and outlet increases stack-driven airflow, and a roof further away delivers less radiant heat to the animals. Overhead hay storage blocks ventilation; wind through the shed is wanted in summer; dust is not the reason.

Question 4 · hard

A tunnel-ventilated poultry house is 12 m wide with an average inside height of 2.8 m. The target air speed is 2.5 m/s and each exhaust fan moves 10 m³/s at the operating static pressure. How many fans are needed?

  1. 8
  2. 9
  3. 3
  4. 17
Answer and working

B. 9

Airflow = 12 × 2.8 × 2.5 = 84 m³/s; 84/10 = 8.4, so 9 fans (round up). 8 fans falls short of the target speed; 3 ignores the height; 17 doubles the requirement for no reason.

Question 5 · easy

Why are standby generators and alarms treated as essential parts of a closed, mechanically ventilated poultry house?

  1. Generators are needed to light the house at night under welfare law everywhere
  2. Alarms warn when egg production drops, which fans cannot otherwise detect
  3. Generators heat the house in summer when the evaporative pads fail
  4. A power cut stops the fans, and birds can die of heat within a short time
Answer and working

D. A power cut stops the fans, and birds can die of heat within a short time

A closed house holding thousands of birds overheats quickly when fans stop, so backup power and failure alarms protect the flock. The other reasons describe functions that are not why backup systems are mandatory parts of the design.

Question 6 · hard

A broiler house in the EU has 1200 m² of usable floor area and is managed to the basic stocking density limit of 33 kg/m² (Directive 2007/43/EC). If birds are sold at 2.2 kg live weight, how many birds can be placed (ignoring mortality)?

  1. 39,600
  2. 21,273
  3. 545
  4. 18,000
Answer and working

D. 18,000

Birds = 1200 × 33 / 2.2 = 18,000. 39,600 is the total kilograms, not birds; 21,273 uses the 39 kg/m² derogation the stem excludes; 545 divides area by weight and forgets the density.

Question 7 · hard

Animals and wet surfaces in a winter barn release 40 kg/h of water vapour. Inside air is to be held at humidity ratio 0.006 kg/kg; outside air is 0.003 kg/kg. Taking ρ = 1.2 kg/m³, what ventilation rate is needed?

  1. 13,333 m³/h
  2. 11,111 m³/h
  3. 5,556 m³/h
  4. 3,704 m³/h
Answer and working

B. 11,111 m³/h

Dry-air flow = 40/(0.0060 − 0.0030) = 13,333 kg/h; volume = 13,333/1.2 = 11,111 m³/h. 13,333 leaves the flow in kg/h; 5,556 uses the inside humidity ratio alone; 3,704 adds the humidity ratios instead of subtracting.

Question 8 · medium

A pesticide store is being added to a farm godown complex. Which requirement is correct?

  1. Placed inside the grain godown so that the chemicals stay dry and secure
  2. Built beside the well so that any spills can be diluted quickly with water
  3. Locked, ventilated and bunded, away from water sources and dwellings
  4. Left unlocked so that any worker can reach the chemicals in an emergency
Answer and working

C. Locked, ventilated and bunded, away from water sources and dwellings

Pesticides are kept in a separate, locked, ventilated, bunded store away from food, water and homes. Storing them with grain or beside a well risks contamination, and unlocked storage risks poisoning.

Question 9 · hard

A storage pond serves 100 cows producing 0.065 m³ of manure each per day, plus 2 m³/day of washwater, for a 180-day storage period. Rainfall on the 800 m² surface during the period is 0.4 m and allowed evaporation is 0.15 m. What storage volume is needed, excluding freeboard?

  1. 1,530 m³
  2. 1,970 m³
  3. 1,370 m³
  4. 1,730 m³
Answer and working

D. 1,730 m³

Manure = 100 × 0.065 × 180 = 1,170 m³; washwater = 2 × 180 = 360 m³; net rain = 800 × (0.40 − 0.15) = 200 m³; total 1,730 m³. 1,530 m³ ignores rain; 1,970 m³ adds evaporation; 1,370 m³ forgets washwater.

Question 10 · hard

An earthen slurry basin is proposed on sandy soil above a shallow aquifer. What is the key design response?

  1. Build the basin deeper, since depth alone stops slurry seeping into the sandy soil
  2. Provide a compacted clay or synthetic liner that limits seepage to the allowed rate
  3. Leave the base unlined so the slurry filters through the sand and is cleaned
  4. Add lime to the slurry, which reliably seals any sandy soil within a few days
Answer and working

B. Provide a compacted clay or synthetic liner that limits seepage to the allowed rate

Sandy soils are permeable, so a liner of compacted clay or a geomembrane is needed to keep seepage within the limit set by the regulator. Depth increases head and seepage; sand does not treat slurry adequately; lime does not reliably seal sand.

A study plan for Agricultural Structures & Environmental Control in Agricultural and Biosystems Engineers Licensure Examination

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (55% of the 38 questions): Poultry housing (5, 13%); Ventilation rate from heat and moisture balance (5, 13%); Farmstead planning (4, 11%); Manure storage structures (4, 11%); Dairy cattle housing (3, 8%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Farm roads and fencing (3, 8%); Space requirements for livestock (3, 8%); Swine housing (3, 8%); Design loads: dead, live, wind, snow and grain (2, 5%); Post-frame buildings (2, 5%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Rat-proof godowns (2, 5%); Rural houses and threshing floors (1, 3%); Structural design of bins and silos (1, 3%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Rural houses and threshing floors (1 hard of 1), Structural design of bins and silos (1 hard of 1), Manure storage structures (3 hard of 4).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Ventilation rate from heat and moisture balance (3 easy of 5); Post-frame buildings (1 easy of 2).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — Agricultural and Biosystems Engineers Licensure Examination Agricultural Structures & Envi

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.