Original practice questions written to the published syllabus · not past papersAgricultural and Biosystems Engineers Licensure Examination (ABELE) is a licensing and registration exam run by Professional Regulatory Board of Agricultural and Biosystems Engineering, PRC, for candidates in Philippines. Paper-based, 2 days (Day 1 6 hours; Day 2 5 hours + 4 hours). Non-programmable calculator only; the Dec 2025 programme bans the Casio fx-991ES/ES Plus by name.
Source: prc.gov.ph.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
Choosing, sizing, costing and replacing machines, and running a custom hiring centre that pays.
Our 26 Agricultural and Biosystems Engineers Licensure Examination questions in this subject: 4 easy, 17 medium, 5 hard, across 11 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to Agricultural and Biosystems Engineers Licensure Examination and are not shown on any other exam's page.
A 3-bottom mouldboard plough with 35 cm bottoms works at 4.5 km/h with 80 % field efficiency. How many hours of field time are needed to plough 12 ha?
C. 31.7 h
Width = 3 × 0.35 = 1.05 m; theoretical capacity = 4.5 × 1.05 / 10 = 0.4725 ha/h; effective = 0.378 ha/h; time = 12 / 0.378 = 31.7 h. 25.4 h ignores efficiency; 20.3 h multiplies area by efficiency instead of dividing, which makes the job look shorter when losses should make it longer. 3.17 h is a factor-of-ten slip.
A farm must harvest 60 ha with a machine of 1.5 ha/h effective capacity, working 10 h per day. Only 60 % of days are fit for harvest. How many calendar days should be planned?
B. 7 days
Days = 60 / (1.5 × 10 × 0.6) = 6.67, rounded up to 7. Ignoring the workable-day probability gives 60 / 15 = 4 days, which assumes every day is fit to work. 10 days divides the 4 fit-day answer by the 40 % unfit fraction instead of the 60 % fit fraction (4/0.4); 3 days multiplies by 0.6 instead of dividing (2.4, rounded up).
A harvest system has a combine able to harvest 4 t/h, two trailers able to haul 3 t/h in total, and a dryer drying 5 t/h. What is the capacity of the system?
D. 3 t/h
In a sequential chain the slowest link sets the pace: haulage at 3 t/h. The combine will wait for trailers, so buying a bigger combine would not raise output; adding haulage would. 5 t/h takes the fastest link (the dryer), 4 t/h the combine, and 12 t/h adds all three.
Why is housing cost charged in a machinery budget even for a farm that keeps its machines in the open?
D. Unhoused machines deteriorate faster and lose resale value
The housing charge stands for either the cost of a shed or the extra depreciation and repair from weather exposure. It is a fixed cost, not a tax and not linked to hours.
An illustrative planning relation gives average diesel use of about 0.223 L/h per kW of a tractor's maximum PTO power. What average consumption does it predict for a tractor with 60 kW maximum PTO power?
C. 13.4 L/h
Consumption = 0.223 × 60 = 13.4 L/h. Dividing 60 by 0.223 inverts the relation; 3.54 is the result converted to US gallons, not litres. The relation is an average over typical loads; actual use depends on load and must come from logs or test data. 269 L/h is that inversion (60/0.223); 1.34 L/h is a decimal slip.
A tractor costing 700,000 is used 1,000 h/yr. Repair and maintenance are 10 % of price per year; it uses 5 L/h of diesel at 90/L; lubrication is 15 % of fuel cost; the operator costs 80/h. What is its variable cost per hour?
B. 667.5/h
R&M = 70,000/1,000 = 70; fuel = 450; lubrication = 67.5; operator = 80. Total = 667.5 per hour. Omitting lubrication gives 600.0; omitting the operator gives 587.5; spreading R&M over 100 h gives 1297.5.
Owning a reaper costs 45,000 a year in fixed costs plus 700/ha in variable costs; custom hire costs 1,600/ha. A farmer harvests 30 ha per year. Which choice is cheaper and by how much?
D. Hiring, by 18,000
Owning = 45,000 + 700 × 30 = 66,000; hiring = 1,600 × 30 = 48,000. Hiring saves 18,000, as expected since 30 ha is below the 50 ha break-even. Comparing hire cost with variable cost alone (27,000) ignores fixed cost.
A machine costs 1,000,000. Its resale values at the end of years 1–6 are 800,000; 680,000; 580,000; 500,000; 430,000; 370,000. Repairs in years 1–6 are 20,000; 40,000; 70,000; 110,000; 160,000; 220,000. Ignoring interest, after how many years should it be replaced?
A. 3 years
Average annual cost for n years = [(P − resale_n) + Σ repairs]/n: n = 1: 220,000; n = 2: 190,000; n = 3: 183,333; n = 4: 185,000; n = 5: 194,000; n = 6: 208,333. The minimum is at n = 3. Year 4 is close (185,000) but higher.
An old combine is cheap to own but breaks down for several days in most harvests, causing shattering losses. In a replacement analysis, these losses should be:
A. Added to the old machine's cost of keeping it another year
Downtime in the critical window causes a timeliness loss that is a direct consequence of keeping the old machine, so it belongs in its marginal cost. Leaving it out biases the decision toward keeping unreliable machines.
The Philippine law that provides the framework for agricultural and fisheries mechanisation, including standards and testing, is:
C. Republic Act 10601
RA 10601 (2013) is the Agricultural and Fisheries Mechanization Law. RA 10915 regulates the practice of agricultural and biosystems engineering; RA 11203 is the rice tariffication law that created the Rice Competitiveness Enhancement Fund; RA 8435 is the earlier Agriculture and Fisheries Modernization Act.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Do these early in revision so they are fast on the day.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.