Original practice questions written to the published syllabus · not past papersICAR AICE-JRF/SRF (PhD) — Agricultural Engineering subjects 38–43 is a PhD, fellowship and lectureship exam run by National Testing Agency for ICAR, for candidates in India. LAN-based computer test, 2 hours, 120 MCQs: 20 Part A (general knowledge and reasoning), 50 Part B (core group), 50 Part C (specialisation); four options.
Source: icar.org.in.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
Project planning and management for processing plants: DPR structure, financial indicators (NPV, IRR, B/C, payback, break-even capacity, DSCR), CPM and PERT computations, and linear programming formulation and duality.
Money and time in engineering decisions: discounting, costs, break-even, project appraisal, scheduling and starting a business.
Our 42 ICAR AICE-JRF/SRF questions in this subject: 9 easy, 16 medium, 17 hard, across 9 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to ICAR AICE-JRF/SRF and are not shown on any other exam's page.
A processing plant has 500 lamps that fail at random. Replacing a lamp individually after failure costs much more per lamp than replacing all lamps together. Under the standard group-replacement rule, when should all lamps be replaced?
D. At the end of period t if individual replacements in period t + 1 would cost more than the average cost per period up to t
Group replacement trades away the remaining life of working lamps for a lower cost per lamp and fewer emergency replacements. The best interval minimises average cost per period; the rule stated finds that interval. Replacing every period ignores that working lamps are discarded too often.
In the economic (as opposed to financial) analysis of an irrigation project, how is a government subsidy on pump sets treated?
C. It is excluded as a transfer, and pump sets are valued at their economic cost
Taxes, subsidies and loan transactions move purchasing power between groups without using real resources, so economic analysis removes them and values inputs at their economic or shadow prices. The financial analysis, from the farmer's viewpoint, does include the subsidy.
What is the main purpose of a pre-feasibility study?
C. To screen a project idea quickly from secondary data before paying for a full study
A pre-feasibility study decides whether an idea deserves the cost of a detailed feasibility study. Detailed design, ex-post evaluation and loan negotiation come at later stages of the project cycle.
A project protected by import duties shows a financial IRR of 18 % but an economic IRR of 6 %. What does this most directly suggest?
C. That protection makes it pay its owner while it uses resources inefficiently for society
Financial and economic IRRs differ when market prices differ from economic values. Protection raises the price the owner receives above the border price, inflating financial returns; at border prices the project earns little. Neither rate must exceed the other in general.
Activities and durations in days, with predecessors: A 4 (none), B 6 (none), C 5 (after A), D 3 (after A), E 4 (after B and D), F 2 (after C and E). What is the free float of activity B?
C. 1 day
Free float = earliest start of the successor − EF of the activity. B finishes at 6 at the earliest; its successor E cannot start before 7 because of D. Free float = 7 − 6 = 1 day, which here equals its total float. 2 days is C's float; 6 days is B's duration. 0 days assumes B lies on the critical path.
An activity has a normal time of 10 days at a cost of 50,000 and a crash time of 6 days at a cost of 70,000. What is its cost slope?
A. 5,000 per day
Cost slope = (crash cost − normal cost)/(normal time − crash time) = (70,000 − 50,000)/(10 − 6) = 5,000 per day. 2,000 divides by the normal time; 7,000 divides the whole crash cost by 10; 11,667 divides crash cost by 6 days.
To shorten a project by one day at least cost, which activity should be crashed first: critical activity P (cost slope 4,000 per day), critical activity Q (2,500 per day), critical activity R (6,000 per day) or non-critical activity S (1,000 per day)?
D. Q, the critical activity with the lowest cost slope
Only shortening a critical activity reduces project duration; crashing S spends money and saves nothing. Among critical activities, crash the one with the lowest cost slope first, then recompute the critical path because another path may become critical.
The primal LP maximises profit subject to 'less than or equal to' resource constraints with non-negative variables. Its dual is:
A. A minimisation with 'greater than or equal to' constraints and the same optimal value
For a standard maximisation primal, the dual minimises the resource values subject to ≥ constraints, one per primal variable. At optimality the objective values are equal (strong duality). The dual has as many variables as the primal has constraints.
In a transportation problem, total supply from the depots is 900 t and total demand at the markets is 750 t. What is done before solving?
A. Add a dummy market with a demand of 150 t and zero transport cost
Supply exceeds demand by 150 t, so a dummy destination with demand 150 t and zero cost absorbs the surplus; goods 'shipped' to it are simply not shipped. A dummy source is used when demand exceeds supply.
Which method for an initial transportation solution uses penalties, the difference between the two lowest costs in each row and column?
A. Vogel's approximation method
Vogel's method allocates first to the row or column with the largest penalty, which gives a starting solution close to optimal. The north-west corner rule ignores costs; MODI and stepping-stone are used to test and improve a solution, not to start one.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Do these early in revision so they are fast on the day.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.