LAISHA
Open Laisha

Rajasthan PSC Surveying & Levelling: practice questions

Rajasthan PSC — Assistant Agriculture Engineer (Agriculture Engineering syllabus) · India · Rajasthan Public Service Commission

Original practice questions written to the published syllabus · not past papers
10worked here, free
89written to this exam in this subject
12syllabus units

About Rajasthan PSC

Rajasthan PSC — Assistant Agriculture Engineer (Agriculture Engineering syllabus) is a government recruitment exam run by Rajasthan Public Service Commission, for candidates in India. Objective paper; the paper structure was not captured.

Source: rpsc.rajasthan.gov.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Surveying & Levelling in Rajasthan PSC

Degree-standard recall and computation: chain survey and obstacles, compass and local attraction, plane-table resection, levelling book reduction, contouring for bunds and terraces, land development and levelling design, and total station.

Measuring land, levels and volumes, from chain survey to total station and GNSS, and designing land grading.

Our 89 Rajasthan PSC questions in this subject: 42 easy, 39 medium, 8 hard, across 12 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to Rajasthan PSC and are not shown on any other exam's page.

Question 1 · hard

In a compass traverse, the fore and back bearings of line PQ are 76°30′ and 256°30′, while those of QR are 118°00′ and 299°30′. Which conclusion is correct?

  1. All stations are free because PQ closes
  2. Q is affected by local attraction
  3. P and Q are free from local attraction; R is affected
  4. P is affected; Q and R are free
Answer and working

C. P and Q are free from local attraction; R is affected

PQ's bearings differ by exactly 180°, so both P and Q are free. At Q the fore bearing of QR (118°00′) is therefore correct, so the correct back bearing at R is 298°00′; the observed 299°30′ shows R is affected by +1°30′, and all bearings observed at R need −1°30′.

Question 2 · medium

In Lehmann's method of solving the three-point problem, the plane-table station is inside the great triangle formed by the three ground stations. Where does the required point lie?

  1. Outside the triangle of error
  2. At any vertex of the triangle of error
  3. Inside the triangle of error
  4. On the side of the triangle of error nearest the most distant station
Answer and working

C. Inside the triangle of error

Lehmann's first rule: if the station is inside the great triangle, the point lies inside the triangle of error; if outside, outside. The distances from the rays are then proportional to the distances of the corresponding stations.

Question 3 · easy

In the rise-and-fall method, a staff reading of 1.265 m is followed by a reading of 2.110 m from the same set-up. What does this indicate?

  1. A rise of 0.845 m
  2. A fall of 3.375 m
  3. A rise of 3.375 m
  4. A fall of 0.845 m
Answer and working

D. A fall of 0.845 m

The second reading is larger, so the second point is lower: fall = 2.110 − 1.265 = 0.845 m. A larger staff reading means more staff below the line of sight, i.e. lower ground. 3.375 m adds the two readings instead of subtracting them.

Question 4 · hard

A level line of 4 km closes on a benchmark with a misclosure of 24 mm. The job specification allows 12√K mm (K in km). What should the engineer do?

  1. Distribute the whole 24 mm to the last change point
  2. Accept it without any adjustment, because the misclosure is within the allowed tolerance
  3. Reject it and re-run the line
  4. Accept it and distribute the 24 mm among change points in proportion to distance
Answer and working

D. Accept it and distribute the 24 mm among change points in proportion to distance

Allowable = 12√4 = 24 mm, so the misclosure is just within the specification. An accepted misclosure is distributed progressively along the line (in proportion to distance or number of set-ups); putting it all on one point or leaving it unadjusted spoils the RLs of intermediate points. The constant in C√K varies by agency, so the job specification governs.

Question 5 · easy

Refraction correction in levelling is commonly taken as what fraction of the curvature correction, and with what sign?

  1. Seven times, opposite in sign
  2. One-seventh, same sign
  3. One-half, opposite in sign
  4. One-seventh, opposite in sign
Answer and working

D. One-seventh, opposite in sign

Refraction bends the sight towards the earth, reducing the curvature effect; it is taken as about 1/7 of curvature, i.e. +0.0112d² against −0.0785d². The value is an average that varies with atmospheric conditions.

Question 6 · easy

For a closed traverse the sum of latitudes is +0.36 m and the sum of departures is −0.48 m. What is the closing error?

  1. 0.12 m
  2. 0.60 m
  3. 0.84 m
  4. 0.36 m
Answer and working

B. 0.60 m

e = √(ΣL² + ΣD²) = √(0.36² + 0.48²) = 0.60 m. Adding magnitudes gives 0.84 m and summing the signed values 0.12 m; 0.36 is the sum of the squares (0.1296 + 0.2304) with the square root forgotten.

Question 7 · hard

A contractor used RTK GNSS heights (ellipsoidal) directly to design the outlet of a drain that must discharge into a channel whose invert is given relative to the national mean-sea-level benchmark. What is the main risk, and the remedy?

  1. Only the horizontal coordinates are affected; RTK heights are already on the benchmark datum
  2. Heights are on different datums; convert via a geoid model or calibrate RTK on local benchmarks
  3. No risk: GNSS heights are always above mean sea level
  4. The only risk is multipath near the channel; re-observe the outlet points at night when it is lower
Answer and working

B. Heights are on different datums; convert via a geoid model or calibrate RTK on local benchmarks

GNSS heights are referred to the ellipsoid, while benchmark levels are orthometric (mean sea level). The difference (geoid undulation) can be tens of metres, and even its slope over a site can matter for low-gradient drains. A geoid model or a site calibration on benchmarks puts both on one datum.

Question 8 · easy

A triangular plot from a chain survey has sides 65, 80 and 95 m. What is its area?

  1. 2600.0 m²
  2. 2569.0 m²
  3. 3800.0 m²
  4. 1284.5 m²
Answer and working

B. 2569.0 m²

Heron's formula: s = (65 + 80 + 95)/2 = 120 m; A = √[s(s − a)(s − b)(s − c)] = √[120 × 55 × 40 × 25] = 2569.0 m². Half the product of two sides (2600 m²) assumes a right angle, which these sides do not form. 3800.0 m² takes the two longer sides (80 and 95 m) as perpendicular; 1284.5 m² halves Heron's result.

Question 9 · medium

India's regional satellite navigation system is called

  1. NavIC
  2. Galileo
  3. GLONASS
  4. QZSS
Answer and working

A. NavIC

NavIC (Navigation with Indian Constellation, formerly IRNSS) is India's regional system. QZSS is Japan's regional system; Galileo and GLONASS are global systems of the EU and Russia.

Question 10 · medium

A laser-levelled rice basin is being checked after levelling. Which survey check best shows whether the job meets the design?

  1. Measure the field perimeter with a tape
  2. Count the scraper passes
  3. Re-survey the grid and compare each station's elevation with its design elevation against the specified tolerance
  4. Check the laser transmitter's battery log
Answer and working

C. Re-survey the grid and compare each station's elevation with its design elevation against the specified tolerance

Quality is judged by the departure of the finished surface from the design at the grid stations, using the tolerance in the contract or standard. Machine hours and perimeter say nothing about surface accuracy.

A study plan for Surveying & Levelling in Rajasthan PSC

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (40% of the 89 questions): Chain and tape surveying, including tape corrections (10, 11%); Compass traversing and bearings (9, 10%); Theodolite traversing and closing error (9, 10%); Contouring (8, 9%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Levelling: rise-and-fall and height-of-instrument methods (8, 9%); Computation of area: trapezoidal and Simpson's rules (7, 8%); Earthwork volume computation (7, 8%); GPS/GNSS surveying (7, 8%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Plane table surveying (7, 8%); Reciprocal levelling (6, 7%); Total station (6, 7%); Land grading and levelling design (5, 6%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Compass traversing and bearings (3 hard of 9), Land grading and levelling design (1 hard of 5), Total station (1 hard of 6).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Land grading and levelling design (3 easy of 5); Plane table surveying (4 easy of 7).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — Rajasthan PSC Surveying & Levelling

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.