Original practice questions written to the published syllabus · not past papersNCEES PE Agricultural and Biological Engineering is a licensing and registration exam run by NCEES (ASABE is the content partner), for candidates in USA. Computer-based, 85 questions, 9.5-hour appointment (8.5 hours of exam). Once a year (next: 28 Oct 2026). Closed book with the electronic NCEES handbook and supplied searchable ASABE standards; SI and US customary units.
Source: ncees.org.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
Surveying appears within common system applications: layout and grade staking, earthwork volumes, pond and channel grades, and interpretation of survey data in US customary or SI units.
Measuring land, levels and volumes, from chain survey to total station and GNSS, and designing land grading.
Our 20 NCEES PE Agricultural and Biological Engineering questions in this subject: 0 easy, 10 medium, 10 hard, across 9 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to NCEES PE Agricultural and Biological Engineering and are not shown on any other exam's page.
A staff is read from a level. The staff reading is 3.000 m when held vertical, but the staff was actually tilted 3° from the vertical in the direction of sight. What reading was observed (to 3 decimals), and what is the lesson?
C. 3.004 m; a tilted staff always reads too high
The horizontal line cuts the tilted staff at a graduation of 3.000/cos 3° = 3.004 m. Tilt in any direction increases the reading, which is why the staffman rocks the staff and the minimum reading is taken.
A graded channel is to be traced on a gradient of 1 in 400 falling downstream, with pegs every 20 m. By how much must the staff reading increase from one peg to the next?
A. 50 mm
Fall per peg = 20/400 = 0.050 m = 50 mm; each successive peg is lower, so the staff reading increases by that amount. The other options are unit or inversion slips. 5.0 mm is a factor-of-ten slip; 25 mm halves it.
An engineer must set out the corners of a farm pond from design coordinates using a total station. Which on-board function is used?
C. Stake-out
Stake-out computes the bearing and distance from the occupied station to each design point and guides the prism holder onto it. Missing-line measures between two observed points; remote elevation finds heights of inaccessible objects.
A surveyor occupies an unknown point and observes angles and distances to two or more control points of known coordinates to fix the instrument's position. This total-station procedure is called
B. resection (free-station set-up)
Resection computes the occupied station's coordinates (and orientation) from observations to known points, which lets the instrument be placed wherever it has a good view. Intersection fixes a distant point from two known stations; ordinary orientation requires the instrument to be on a known point.
Which GNSS technique gives centimetre-level positions in real time for staking out a land-grading design?
D. Real-time kinematic (RTK) with a base station or reference network
RTK uses carrier-phase corrections from a base or network sent by radio or internet, and resolves positions to a few centimetres in seconds. Autonomous positioning is metre-level; code DGPS is sub-metre to metre; static gives very high accuracy but only after processing, not in real time.
A four-sided field has corner coordinates (E, N) in metres of A(0, 0), B(120, 10), C(140, 95) and D(30, 110). What is its area?
D. 11275 m²
Shoelace: ½|Σ(xi yi+1 − xi+1 yi)| = ½|(0×10 − 120×0) + (120×95 − 140×10) + (140×110 − 30×95) + (30×0 − 0×110)| = ½|0 + 10,000 + 12,550 + 0| = 11275 m² (1.1275 ha). Forgetting the half doubles the answer; halving twice gives 5638 m²; 120 × 110 treats the field as a rectangle. 22550 m² forgets the half; 13200 m² is 120 × 110.
A borrow pit is laid out as four 10 m × 10 m squares (a 2 × 2 grid). Depths of cut at the four outer corners are 1.2, 0.8, 1.0 and 1.4 m; at the four mid-side points 1.1, 0.9, 1.3 and 1.2 m; and at the centre point 1.05 m. What is the volume of excavation?
C. 440.0 m³
V = (A/4)(Σh1 + 2Σh2 + 4Σh4) with A = 100 m²: Σh1 = 4.4, Σh2 = 4.5, h4 = 1.05. V = 25(4.4 + 9.0 + 4.2) = 440.0 m³. Averaging all nine depths over 400 m² (442.2 m³) ignores how many squares share each corner. 248.8 m³ applies A/4 without the 2 and 4 weights; 1760.0 m³ uses A = 400 m² instead of 100 m².
A land-grading design gives total cut 1450 m³ and total fill 1320 m³. The engineer wants a cut:fill ratio of about 1.3 for this soil. What should be done?
D. Lower the design plane slightly and recompute until cut/fill reaches about 1.3
Current ratio = 1450/1320 = 1.10, below the target. Lowering the plane increases every cut and reduces every fill, raising the ratio; raising it would lower the ratio. The ratio allows for settlement and losses and its value depends on soil and conditions.
The whole-circle bearings of lines AB and AC are 38°45′ and 301°30′. What is the angle BAC (the smaller angle between the two lines)?
A. 97°15′
Difference = 301°30′ − 38°45′ = 262°45′; the smaller angle between the lines is 360° − 262°45′ = 97°15′. 262°45′ is the reflex angle.
For a topographic survey for land grading, when is a total station preferred over RTK GNSS?
C. Where tree cover, buildings or steep banks block satellite signals
RTK needs a clear view of enough satellites and a correction link; under canopy or beside tall obstructions it may fail or give poor fixes, and a total station works by line of sight to a prism. On open fields RTK is usually faster. GNSS does give heights, but ellipsoidal ones.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.