GATE — Agricultural Engineering (AG) · India · IITs and IISc on rotation (2027: IIT Madras)
Original practice questions written to the published syllabus · not past papersGATE — Agricultural Engineering (AG) is a postgraduate admission exam run by IITs and IISc on rotation (2027: IIT Madras), for candidates in India. Computer-based, 3 hours, 100 marks (15 General Aptitude + 85 technical: 25 one-mark and 30 two-mark questions). MCQ, MSQ and NAT; negative marking on MCQ only (−1/3 for one-mark, −2/3 for two-mark); no partial credit on MSQ. On-screen virtual calculator.
Source: gate2027.iitm.ac.in.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
Sources of Power section: short numericals rather than theory. Biogas plant sizing (digester volume from dung, dilution and HRT; daily gas; gas holder) has appeared in a minority of recent papers; expect also heating-value, gasifier efficiency and ethanol or biodiesel stoichiometry at one or two marks. Units and bases (wet vs dry, kWh vs MJ) decide marks.
Turning crop residues, dung and oils into fuel: briquettes, gasifiers, biogas plants and liquid biofuels, and auditing farm energy.
Our 42 GATE questions in this subject: 7 easy, 25 medium, 10 hard, across 13 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to GATE and are not shown on any other exam's page.
A biomass sample analyses (as received) moisture 12%, volatile matter 62%, ash 8%, with fixed carbon by difference. Its volatile matter on a dry ash-free (daf) basis is:
B. 77.5%
Fixed carbon = 100 − 12 − 62 − 8 = 18%. On a daf basis only VM and FC remain: VM_daf = 62 ÷ (62 + 18) × 100 = 62 ÷ 0.80 = 77.5%. Dividing by (1 − moisture) alone gives the dry basis (70.5%), which still contains ash. 67.4% divides by (1 − ash) only: 62 ÷ 0.92.
Using Dulong's formula, HHV (MJ/kg) = 33.8C + 144(H − O/8) + 9.4S with mass fractions, estimate the HHV of a dry biomass with C = 0.48, H = 0.06, O = 0.42, S = 0.001.
A. 17.3 MJ/kg
H − O/8 = 0.06 − 0.42/8 = 0.0075 (the 'available' hydrogen, since oxygen already in the fuel is assumed bound to one-eighth its mass of hydrogen). HHV = 33.8 × 0.48 + 144 × 0.0075 + 9.4 × 0.001 = 16.22 + 1.08 + 0.009 = 17.3 MJ/kg. Ignoring the oxygen correction gives 24.9 MJ/kg, far too high for biomass. Dulong's formula was built for coal and tends to under-predict for oxygen-rich biomass, which is why unified correlations are preferred. 16.2 MJ/kg keeps only the carbon term (33.8 × 0.48); 1.09 MJ/kg leaves the carbon term out.
A biomass furnace fuel has a stoichiometric air–fuel ratio of 5.78 kg/kg and is fired with 40% excess air. The actual air supplied per kg of fuel is:
D. 8.09 kg
Actual air = stoichiometric air × (1 + excess fraction) = 5.78 × 1.40 = 8.09 kg per kg fuel. 2.31 kg is only the excess portion. 4.13 kg divides by 1.40 instead of multiplying; 6.18 kg adds 0.40 kg instead of 40%.
An air-blown gasifier uses 1.3 Nm³ of air per kg of biomass. The dry producer gas contains 50% N2 by volume, and the fuel's own nitrogen is negligible. Using a nitrogen balance (air is 79% N2 by volume), the dry gas yield is:
B. 2.05 Nm³ per kg biomass
N2 is inert, so N2 in = N2 out: 1.3 × 0.79 = 1.027 Nm³ = 0.5 × gas volume. Gas volume = 1.027 ÷ 0.5 = 2.05 Nm³/kg. Dividing the whole air volume by 0.5 (2.60) forgets that air is only 79% nitrogen. The tie-element method is the standard way to close a gasifier mass balance.
Producer gas contains, by volume, CO 20%, H2 18%, CH4 2%, the rest CO2 and N2. The stoichiometric air requirement (air 21% O2 by volume) is:
A. 1.10 m³ air per m³ gas
O2 needed: CO + ½O2 → CO2 gives 0.2 × 0.5; H2 + ½O2 → H2O gives 0.18 × 0.5; CH4 + 2O2 → CO2 + 2H2O gives 0.02 × 2. Total O2 = 0.10 + 0.09 + 0.04 = 0.23 m³/m³. Air = 0.23 ÷ 0.21 = 1.10 m³/m³. Using 0.232 mixes the mass fraction into a volume calculation. The ratio is close to 1:1, which is why producer-gas mixers admit roughly equal volumes of gas and air.
A mild-steel floating gas holder of mass 120 kg and diameter 1.5 m floats freely. The gas pressure under it, expressed in centimetres of water column, is about:
A. 6.8 cm
Area = π × 1.5²/4 = 1.767 m². Pressure = weight ÷ area = 120 × 9.81 ÷ 1.767 = 666 Pa. Head = p ÷ (ρg) = 666 ÷ (1000 × 9.81) = 0.0679 m = 6.8 cm of water. Using π D² as the area cuts the answer to a quarter; forgetting to convert metres to centimetres misplaces the decimal. Extra weights are sometimes added to the drum to raise pressure for distant burners.
A digester is to receive 60 kg of volatile solids per day at a design organic loading rate of 2.0 kg VS per m³ of digester per day. The active digester volume is:
B. 30 m³
Volume = VS load ÷ OLR = 60 ÷ 2.0 = 30 m³. Designers check both criteria, HRT and OLR, and use the larger volume. 120 m³ multiplies instead of dividing; 0.033 m³ inverts the ratio (2 ÷ 60); 15 m³ divides by the loading rate twice (60 ÷ 2 ÷ 2).
A biogas plant produces 3.0 m³ of gas per day, and the gas holder is to store 50% of daily production. The gas holder volume is:
A. 1.5 m³
Storage = 3.0 × 0.5 = 1.5 m³. The storage fraction depends on how gas use is spread through the day: when all cooking happens in two short meals, more storage is needed than when gas is drawn steadily. 6.0 m³ divides by 0.5 instead of multiplying; 4.5 m³ adds 50% to the daily production (3.0 × 1.5).
A floating gas holder must store 1.5 m³ of gas with an effective gas height (drum rise) of 1.0 m. The drum diameter is about:
D. 1.38 m
V = (π D²/4) × H, so D = √(4V ÷ πH) = √(4 × 1.5 ÷ (π × 1.0)) = √1.910 = 1.38 m. Omitting the 4 gives the radius (0.69 m); forgetting the square root gives D².
When 1000 kg of triolein (885.4 g/mol) is completely transesterified, the glycerol (92.09 g/mol) produced is:
D. 104 kg
One mol of triglyceride gives one mol of glycerol: 1.1294 kmol × 92.09 = 104 kg, about 10% of the oil. Three glycerol per triglyceride (312 kg) confuses the ester count with glycerol count; 1005 kg is the methyl oleate produced. 34.7 kg divides the glycerol by three.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Do these early in revision so they are fast on the day.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.