LAISHA
Open Laisha

ASRB NET Watershed Planning & Management: practice questions

ASRB NET — Farm Machinery & Power / Land & Water Management Engineering / Agricultural Structures & Process Engineering · India · Agricultural Scientists Recruitment Board (ICAR)

Original practice questions written to the published syllabus · not past papers
10worked here, free
38written to this exam in this subject
10syllabus units

About ASRB NET

ASRB NET — Farm Machinery & Power / Land & Water Management Engineering / Agricultural Structures & Process Engineering is a specialist certification exam run by Agricultural Scientists Recruitment Board (ICAR), for candidates in India. NET: 150 MCQs, 150 marks, 2 hours, −1/3 per wrong answer, English/Hindi, PG level. Combined NET/ARS/SMS/STO recruitment runs prelims, mains and interview.

Official site: pw.live.

We have not been able to confirm these details against the exam body's own specification, so fees, dates and pass marks are left out on purpose. Check the current format, eligibility, fees and dates on the official site.

Watershed Planning & Management in ASRB NET

Watershed management concepts and standard formulas, programme guidelines and evaluation, at the depth of an M.Tech course.

Planning a whole watershed: delineating it, classifying its land, budgeting its water and choosing harvesting structures with the people who live there.

Our 38 ASRB NET questions in this subject: 1 easy, 19 medium, 18 hard, across 10 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to ASRB NET and are not shown on any other exam's page.

Question 1 · medium

When deriving a stream network from a DEM, lowering the flow-accumulation threshold used to define streams will:

  1. produce a sparser network and a lower drainage density
  2. leave drainage density unchanged because it depends only on the DEM
  3. change the watershed boundary but not the stream network
  4. denser network and higher drainage density
Answer and working

D. denser network and higher drainage density

A lower threshold means fewer upstream cells are needed before a cell is called a stream, so more small channels appear and total stream length per unit area rises. This is why drainage densities from DEMs should only be compared when the same threshold and resolution were used. The boundary itself depends on the pour point, not the threshold.

Question 2 · medium

In the FAO Framework for Land Evaluation, class N1 means land that is:

  1. permanently not suitable for the use, because the limitation can never be overcome
  2. marginally suitable for the use
  3. currently not suitable, although the limitation may be overcome in future
  4. not suitable for any use at all
Answer and working

C. currently not suitable, although the limitation may be overcome in future

FAO suitability classes are S1 (highly), S2 (moderately), S3 (marginally suitable), N1 (currently not suitable; limitations may be overcome later, for example at higher cost) and N2 (permanently not suitable). Suitability is always judged for a defined land utilisation type, not for all uses.

Question 3 · medium

The land capability classification of Klingebiel and Montgomery assumes which of the following?

  1. The highest-value crop that the market will pay for
  2. Moderately high management
  3. Distance to market and land ownership as limiting factors
  4. That land can never be improved by reclamation
Answer and working

B. Moderately high management

LCC interprets physical limitations under a moderately high level of management; it deliberately ignores location, markets, ownership and crop value. Reclamation (drainage, removal of stones) can change the effective class, so land is not assumed to be unchangeable.

Question 4 · hard

What distinguishes the USBR irrigation land classification from a purely physical soil classification?

  1. Classes are defined by capacity to repay the costs of irrigation development, so economics is built in
  2. It uses only soil colour and texture, recorded in the field, and ignores slope, drainage and water supply
  3. It ignores drainage conditions and classifies land solely by the crop yields recorded in the previous season
  4. It applies only to rainfed land
Answer and working

A. Classes are defined by capacity to repay the costs of irrigation development, so economics is built in

The USBR system groups land by payment capacity: its ability to sustain enough net farm income under irrigation to cover costs. Drainage, topography and soil are all assessed, but interpreted in economic terms.

Question 5 · hard

At Sukhomajri in Haryana, a feature that made the community's grazing closure of the catchment work was:

  1. water rights were given only in proportion to land owned, so the largest landowners had the strongest stake
  2. the forest department fenced the catchment with barbed wire and posted armed guards at every entry path
  3. livestock were removed from the village by government order
  4. water from the new dam was shared among all households, including the landless, who could trade shares
Answer and working

D. water from the new dam was shared among all households, including the landless, who could trade shares

The families who gave up grazing in the catchment, including landless households, received a share of the stored water that they could use or sell, so they had a direct interest in protecting the catchment. Rules were set and enforced by the village society, not by fencing or orders.

Question 6 · medium

The correct basis for measuring the benefit of a watershed project in cost-benefit analysis is the comparison:

  1. before the project versus after the project
  2. with the project versus without the project
  3. the treated watershed versus the national average
  4. the project's budget versus its actual expenditure
Answer and working

B. with the project versus without the project

Many things change over time regardless of the project: rainfall, prices, varieties. Only the difference between the situation with the project and the situation that would have existed without it is attributable to the project. A before–after comparison credits the project with changes it did not cause.

Question 7 · medium

In the economic (as opposed to financial) analysis of a watershed project, which adjustment is made?

  1. Subsidies received by farmers are added to benefits, because they increase the farmers' net cash returns
  2. Only cash income of the implementing agency is counted
  3. Transfer payments such as taxes and subsidies are removed and distorted prices are replaced by shadow prices
  4. The discount rate is set to zero for public projects, since society values future benefits as much as present ones
Answer and working

C. Transfer payments such as taxes and subsidies are removed and distorted prices are replaced by shadow prices

Economic analysis takes society's viewpoint: taxes and subsidies transfer money within society and are not real costs or benefits, and inputs like unskilled labour are valued at their opportunity cost (shadow price). Financial analysis, from the farmer's or agency's viewpoint, uses market prices including transfers.

Question 8 · hard

Two mutually exclusive watershed designs are compared at the same discount rate: Design P has NPV 8 million and BCR 1.4; Design Q has NPV 5 million and BCR 1.9. Budget is not a constraint. Which should be chosen, and why?

  1. Design Q, because a higher BCR always indicates the better project, whatever the size of the investment
  2. Design Q, because its costs are lower
  3. Neither, because the two measures disagree
  4. Design P, because among mutually exclusive projects the one with the higher NPV adds more net value
Answer and working

D. Design P, because among mutually exclusive projects the one with the higher NPV adds more net value

BCR and NPV can rank projects of different sizes differently. When only one can be built and capital is not constrained, the higher NPV gives the greatest net benefit to society. BCR is a ratio and favours smaller projects with high returns per unit cost, which matters mainly when budgets are rationed.

Question 9 · easy

The US Soil Conservation Service, created in 1935 after the Dust Bowl, is now called:

  1. the Bureau of Reclamation
  2. the Natural Resources Conservation Service
  3. the Environmental Protection Agency
  4. the Forest Service
Answer and working

B. the Natural Resources Conservation Service

The Soil Conservation Service was renamed the Natural Resources Conservation Service (NRCS) in 1994. The Bureau of Reclamation builds western irrigation and water projects; the EPA and Forest Service are separate agencies.

Question 10 · hard

A common lesson from watershed programmes in India, Ethiopia, Kenya and China is that works on common land and upper slopes last longest when:

  1. the works are built entirely by contractors to a high engineering standard, with no local labour or cost sharing
  2. all livestock are permanently banned from the watershed by law
  3. the project avoids involving local institutions to save time
  4. users hold secure, agreed rights to benefits such as fodder, water or tree produce and help set the rules
Answer and working

D. users hold secure, agreed rights to benefits such as fodder, water or tree produce and help set the rules

Evaluations across countries find that maintenance and protection depend on who benefits: when users gain fodder, water or produce and help make and enforce rules, closures and structures survive. High engineering standard alone does not ensure maintenance, and permanent bans imposed from outside are hard to enforce.

A study plan for Watershed Planning & Management in ASRB NET

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (58% of the 38 questions): Cost-benefit analysis of watershed projects (7, 18%); Watershed characterisation and morphometry (6, 16%); Land capability classification (5, 13%); National watershed programmes (4, 11%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Participatory watershed planning (4, 11%); Land irrigability classification (3, 8%); Rainwater harvesting: check dams, percolation tanks and farm ponds (3, 8%); Roof-top rainwater harvesting (2, 5%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Water budgeting (2, 5%); Watershed delineation (2, 5%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Roof-top rainwater harvesting (2 hard of 2), Land irrigability classification (2 hard of 3), Rainwater harvesting: check dams, percolation tanks and farm ponds (2 hard of 3).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: National watershed programmes (1 easy of 4).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — ASRB NET Watershed Planning & Management

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.